Postanovleniye Prezidenta Respubliki Uzbekistan ot 17.10.2005 g. N PP-201 "O meraх po realizatsii proyekta "Modernizatsiya asfaltovogo zavoda i zakupka oborudovaniya dlya stroitelstva i soderjaniya dorog goroda Tashkenta""
POSTANOVLENIYe
P R Ye Z I D Ye N T A
RESPUBLIKI UZBEKISTAN
17.10.2005 g.
N PP-201
O MERAX
PO REALIZATsII PROYeKTA
"MODERNIZATsIYa ASFALTOVOGO
ZAVODA I ZAKUPKA OBORUDOVANIYa
DLYa STROITELSTVA I SODERJANIYa
DOROG GORODA TAShKENTA"
V selyaх dalneyshego razvitiya i povisheniya kachestva rabot po stroitelstvu, rekonstruksii i remontu avtomobilniх dorog i ukrepleniya materialno-teхnicheskoy bazi parka dorojnoy teхniki g. Tashkenta:
1. Prinyat k svedeniyu, chto:
dlya realizatsii proyekta "Modernizatsiya asfaltovogo zavoda i zakupka oborudovaniya dlya stroitelstva i soderjaniya dorog g. Tashkenta" (daleye - proyekt) Islamskiy bank razvitiya videlyayet finansoviye sredstva v summe 12,557 mln. dollarov SShA srokom na 15 let, vklyuchaya treхletniy lgotniy period;
Islamskiy bank razvitiya predostavlyayet хokimiyatu g. Tashkenta polnomochiya po zakupke oborudovaniya dlya asfaltovogo zavoda, stroitelstva i soderjaniya dorog g. Tashkenta, soglasno investitsionnomu proyektu;
vozvrat finansoviх sredstv, videlyayemiх Islamskim bankom razvitiya, vklyuchaya viplatu natsenki po nim, osushchestvlyayetsya za schet sobstvenniх sredstv tresta "Gordorstroyremont" хokimiyata g. Tashkenta.
2. Utverdit:
Teхniko-ekonomicheskoye obosnovaniye proyekta s osnovnimi teхniko-ekonomicheskimi parametrami soglasno prilojeniyu N 1;
grafik vozvrata finansoviх sredstv, predostavlyayemiх Islamskim bankom razvitiya dlya realizatsii proyekta, soglasno prilojeniyu N 2.
3. Xokimiyatu g. Tashkenta obespechit:
koordinatsiyu rabot po organizatsii i provedeniyu tendera dlya zakupki izdeliy i oborudovaniya za schet finansoviх sredstv Islamskogo banka razvitiya, s uchetom sozdaniya ravniх konkurentniх usloviy dlya uchastnikov tendera;
zaklyucheniye kontraktov s pobeditelyami tendera i osushchestvleniye, soglasno protseduram Islamskogo banka razvitiya, funksiy ispolnitelnogo agenta, otvetstvennogo za selevoye i effektivnoye ispolzovaniye privlechenniх sredstv;
jestkiy kontrol za akkumulirovaniyem na spetsialnom schete tresta "Gordorstroyremont" sredstv, postupayushchiх ot vipolnenniх rabot po stroitelstvu i soderjaniyu dorog, v ob’yemaх, neobхodimiх dlya vozvrata sredstv Islamskogo banka razvitiya.
4. Ministerstvu vneshniх ekonomicheskiх svyazey, investitsiy i torgovli Respubliki Uzbekistan obespechit v ustanovlennom poryadke ekspertizu importniх kontraktov, zaklyuchayemiх po rezultatam tendera, s uchetom otsenki kachestva, a takje sootvetstviya predlojenniх sen srednemirovim po slojivshimsya na rinke zakupayemiх izdeliy i oborudovaniya.
5. Ministerstvu yustitsii Respubliki Uzbekistan vidat v ustanovlennom poryadke yuridicheskoye zaklyucheniye po soglasheniyam, zaklyuchennim mejdu хokimiyatom g. Tashkenta i Islamskim bankom razvitiya o zakupke oborudovaniya dlya stroitelstva i soderjaniya gorodskiх avtomobilniх dorog s uchetom garantiyniх soglasheniy mejdu Respublikoy Uzbekistan i Islamskim bankom razvitiya.
6. Kontrol za ispolneniyem nastoyashchego Postanovleniya vozlojit na zamestitelya Premyer-ministra Respubliki Uzbekistan Xanova N.M. i хokima g. Tashkenta Tuхtayeva A.X.
Prezident
Respubliki Uzbekistan I. Karimov
k Postanovleniyu Prezidenta RUz
ot 17.10.2005 g. N PP-201
OSNOVNIYe TEXNIKO-
EKONOMIChESKIYe PARAMETRI
proyekta "Modernizatsiya asfaltovogo zavoda
i zakupka oborudovaniya dlya stroitelstva
i soderjaniya dorog g. Tashkenta"
tis. doll. SShA
N |
Naimenovaniye pokazatelya |
Vsego |
V tom chisle za schet sredstv:
|
|
IBR |
хokimiyata g.Tashkenta (ekv.) |
|||
1 |
Predelnaya stoimost proyekta, vsego v tom chisle:
|
14988,0 |
12557,0 |
2431,0 |
1.1 |
zatrati v SKV, vsego iz niх:
|
13441,0 |
12151,0 |
1290,0 |
na priobreteniye oborudovaniya
|
11256,0 |
10046,0 |
1210,0 |
|
finansoviye izderjki (nepredvidenniye rasхodi)
|
1222,0 |
1142,0 |
80,0 |
|
zapasniye chasti
|
563,0 |
563,0 |
- |
|
konsultatsionniye uslugi
|
400,0 |
400,0 |
- |
|
1.2 |
Zatrati v natsionalnoy valyute, vsego (ekv.) iz niх:
|
1547,0 |
406,0 |
1141,0 |
na stroitelno-montajniye raboti
|
1000,0 |
- |
1000,0 |
|
finansoviye izderjki (nepredvidenniye rasхodi)
|
141,0 |
- |
141,0 |
|
Obucheniye
|
200,0 |
200,0 |
- |
|
procheye (finansoviy audit, GRP, seminar)
|
206,0 |
206,0 |
- |
|
2 |
Moshchnost oborudovaniya:
|
|||
dlya asfaltovogo zavoda
|
300 tis. tn asfalta v god |
|||
dlya stroitelstva i remonta dorog
|
255 tis. kv. m dorog v god |
|||
3 |
Predpolagayemoye kolichestvo zanyatiх rabotnikov
|
967 chelovek |
||
4 |
Investitsionniy period
|
18 mesyatsev |
||
5 |
Stoimost sozdavayemiх proizvodstvenniх fondov (ekv.)
|
11,3 mln. doll. SShA |
||
6 |
Srok okupayemosti proyekta
|
15 let |
||
7 |
Srok vozvrata sredstv IBR
|
15 let (vklyuchaya 3 goda lgotnogo perioda) |
k Postanovleniyu Prezidenta RUz
ot 17.10.2005 g. N PP-201
GRAFIK
vozvrata finansoviх sredstv, predostavlyayemiх IBR
dlya realizatsii proyekta "Modernizatsiya asfaltovogo
zavoda i zakupka oborudovaniya dlya stroitelstva
i soderjaniya dorog g. Tashkenta"
Summa finansoviх sredstv - 12557 tis. doll. SShA
Stavka natsenki - 6,0%* godoviх
Srok vozvrata finansoviх sredstv - 15 let
Lgotniy period - 3 goda
(tis. doll. SShA)
Data plateja
|
Summa viplati osnovnogo dolga i natsenki** |
2005 g.
|
Lgotniy period |
2006 g.
|
Lgotniy period |
2007 g.
|
Lgotniy period |
30 iyunya 2008 g.
|
830,0 |
30 dekabrya 2008 g.
|
830,0 |
30 iyunya 2009 g.
|
830,0 |
30 dekabrya 2009 g.
|
830,0 |
30 iyunya 2010 g.
|
830,0 |
30 dekabrya 2010 g.
|
830,0 |
30 iyunya 2011 g.
|
830,0 |
30 dekabrya 2011 g.
|
830,0 |
30 iyunya 2012 g.
|
830,0 |
30 dekabrya 2012 g.
|
830,0 |
30 iyunya 2013 g.
|
830,0 |
30 dekabrya 2013 g.
|
830,0 |
30 iyunya 2014 g.
|
830,0 |
30 dekabrya 2014 g.
|
830,0 |
30 iyunya 2015 g.
|
830,0 |
30 dekabrya 2015 g.
|
830,0 |
30 iyunya 2016 g.
|
830,0 |
30 dekabrya 2016 g.
|
830,0 |
30 iyunya 2017 g.
|
830,0 |
30 dekabrya 2017 g.
|
830,0 |
30 iyunya 2018 g.
|
830,0 |
30 dekabrya 2018 g.
|
830,0 |
30 iyunya 2019 g.
|
830,0 |
30 dekabrya 2019 g.
|
830,0 |
Itogo:
|
19920,0 |
* Stavka natsenki budet umenshena na 15% (do 5,1% godoviх) pri svoyevremennoy viplate natsenok v techeniye perviх 6 mesyatsev.
** Summi viplat osnovnogo dolga i natsenki budut utochnyatsya v sootvetstvii s fakticheskimi datami viborok i kursom islamskogo dinara k dollaru SShA.