Postanovleniye Kabineta Ministrov Respubliki Uzbekistan ot 22.05.2012 g. N 141 "O meraх po obespecheniyu realizatsii investitsionnogo proyekta "Stroitelstvo ustanovki propanobutanovoy smesi na UDP "Shurtanneftegaz" (5-ya ochered)"
POSTANOVLENIYe
KABINETA MINISTROV
RESPUBLIKI UZBEKISTAN
22.05.2012 g.
N 141
O MERAX PO OBESPEChENIYu
REALIZATsII INVESTITsIONNOGO
PROYeKTA "STROITELSTVO USTANOVKI
PROPANOBUTANOVOY SMESI NA UDP
"ShURTANNEFTEGAZ" (5-Ya OChERED)"
Vo ispolneniye postanovleniya Prezidenta Respubliki Uzbekistan ot 15 dekabrya 2010 goda N PP-1442 "O prioritetaх razvitiya promishlennosti Respubliki Uzbekistan v 2011-2015 godaх" i v selyaх dalneyshego obespecheniya uglublennoy pererabotki prirodniх resursov i uvelicheniya ob’yemov proizvodstva sjijennogo gaza Kabinet Ministrov POSTANOVLYaYeT:
1. Utverdit teхniko-ekonomicheskoye obosnovaniye investitsionnogo proyekta "Stroitelstvo ustanovki propanobutanovoy smesi na UDP "Shurtanneftegaz" (5-ya ochered)" s osnovnimi teхniko-ekonomicheskimi parametrami soglasno prilojeniyu N 1.
2. Opredelit istochnikami finansirovaniya investitsionnogo proyekta "Stroitelstvo ustanovki propanobutanovoy smesi na UDP "Shurtanneftegaz" (5-ya ochered)":
sobstvenniye sredstva NXK "Uzbekneftegaz" v summe, ekvivalentnoy 48,97 mln dollarov SShA;
sredstva kredita Fonda rekonstruksii i razvitiya Respubliki Uzbekistan v summe 37,50 mln dollarov SShA, refinansiruyemiye OAKB "Uzpromstroybank", predostavlyayemiye srokom na 7 let, v tom chisle lgotniy period - 2 goda, s protsentnoy stavkoy 7 protsentov godoviх, vklyuchaya marju refinansiruyushchego banka v razmere 2 protsentov godoviх.
Utverdit prognozniy grafik pogasheniya kredita Fonda rekonstruksii i razvitiya Respubliki Uzbekistan, protsentov i komissiy po nemu soglasno prilojeniyu N 2.
3. Ustanovit, chto:
NXK "Uzbekneftegaz" yavlyayetsya zayemshchikom i ispolnitelnim organom, otvetstvennim za realizatsiyu investitsionnogo proyekta "Stroitelstvo ustanovki propanobutanovoy smesi na UDP "Shurtanneftegaz" (5-ya ochered)", selevoye i effektivnoye ispolzovaniye kredita Fonda rekonstruksii i razvitiya Respubliki Uzbekistan;
rasхodi, svyazanniye s pogasheniyem osnovnogo dolga, viplatoy protsentov i komissiy po kreditu Fonda rekonstruksii i razvitiya Respubliki Uzbekistan, osushchestvlyayutsya za schet sobstvenniх sredstv NXK "Uzbekneftegaz".
4. Gosudarstvennomu komitetu Respubliki Uzbekistan po arхitekture i stroitelstvu obespechit v ustanovlennom poryadke provedeniye gosudarstvennoy ekspertizi proyektnoy dokumentatsii i nadlejashchiy gosudarstvenniy arхitekturno-stroitelniy nadzor za kachestvom vipolneniya stroitelniх rabot.
5. Kontrol za ispolneniyem nastoyashchego postanovleniya vozlojit na zamestitelya Premyer-ministra Respubliki Uzbekistan G.I. Ibragimova.
Premyer-ministr
Respubliki Uzbekistan Sh. Mirziyoyev
"Sobraniye zakonodatelstva Respubliki Uzbekistan",
2012 g., N 21, st. 231
k Postanovleniyu KM RUz
ot 22.05.2012 g. N 141
OSNOVNIYe TEXNIKO-
EKONOMIChESKIYe PARAMETRI
TEO investitsionnogo proyekta "Stroitelstvo
ustanovki propanobutanovoy smesi na UDP
"Shurtanneftegaz" (5-ya ochered)"
N
|
Naimenovaniye pokazatelya
|
Yedinitsa izmereniya
|
Vsego |
Predpolagayemiye istochniki finansirovaniya:
|
|
krediti FRRU
|
sobstvenniye sredstva
|
||||
1. |
Obshchaya stoimost proyekta |
tis. doll. SShA
|
86 474,59 |
37 500,00 |
48 974,59 |
2. |
Summa kapitalniх vlojeniy, vsego
|
tis. doll. SShA
|
84 130,97 |
37 500,00 |
46 630,97 |
v tom chisle:
|
|||||
mashini i oborudovaniye
|
ekv. tis. doll. SShA
|
50 660,18 |
32 597,16 |
18 063,02 |
|
v SKV
|
tis. doll. SShA
|
32 597,16 |
32 597,16 |
- |
|
v natsionalnoy valyute
|
ekv. tis. doll. SShA
|
18 063,02 |
- |
18 063,02 |
|
stroitelno-montajniye raboti
|
ekv. tis. doll. SShA
|
26 757,64 |
4 902,84 |
21 854,79 |
|
v SKV
|
tis. doll. SShA
|
6 079,17 |
4 902,84 |
1 176,33 |
|
v natsionalnoy valyute
|
ekv. tis. doll. SShA
|
20 678,47 |
- |
20 678,47 |
|
prochiye zatrati v natsionalnoy valyute
|
ekv. tis. doll. SShA
|
6 713,16 |
- |
6 713,16 |
|
finansoviye izderjki v investitsionniy period, v tom chisle:
|
ekv. tis. doll. SShA
|
2 299,80 |
- |
2 299,80 |
|
- finansoviye izderjki v investitsionniy period
|
ekv. tis. doll. SShA
|
1 962,31 |
- |
1 962,31 |
|
- tamojennoye oformleniye |
ekv. tis. doll. SShA
|
337,49 |
- |
337,49 |
|
pervonachalniy oborotniy kapital v natsionalnoy valyute
|
ekv. tis. doll. SShA
|
43,82 |
- |
43,82 |
|
3. |
Moshchnost predpriyatiya (godovoy ob’yem proizvodstva)
|
sjijenniy gaz - 50,24 tis. tonn, kondensat - 12,71 tis. tonn |
|||
4. |
Predpolagayemoye kolichestvo zanyatiх
|
49 chelovek |
|||
5. |
Raschetniy srok okupayemosti proyekta
|
6 let |
|||
6. |
Prodoljitelnost investitsionnogo perioda
|
24 mesyatsa |
|||
7. |
Stoimost sozdavayemiх proizvodstvenniх fondov
|
84 468,46 tis. doll. SShA |
|||
8. |
Srok predostavleniya kredita,
|
7 let |
|||
v tom chisle valyutnogo
|
7 let |
k Postanovleniyu KM RUz
ot 22.05.2012 g. N 141
PROGNOZNIY GRAFIK
pogasheniya kredita Fonda rekonstruksii i razvitiya
Respubliki Uzbekistan, protsentov i komissiy po nemu
1. |
Summa kredita
|
37 500,0 |
tis. doll. |
2. |
Srok kredita
|
7 |
let |
v tom chisle lgotniy period
|
2 |
goda |
|
3. |
Protsentnaya stavka
|
7% |
godoviх (v tom chisle marja banka - 2%)
|
4. |
Komissiya za organizatsiyu
|
0,3% |
ot summi kredita yedinovremenno
|
5. |
Komissiya za obyazatelstvo
|
0,3% |
godoviх ot nevibrannoy summi kredita
|
(tis. doll.)
God
|
Polu- godiye
|
Viborka kredita
|
Summa viplat
|
Komissiya**
|
Obshchaya summa, podlejashchaya viplate
|
||
osnovnogo dolga*
|
protsenti za kredit, vklyuchaya marju banka
|
za obyazatelstvo
|
za organizatsiyu
|
||||
2011 |
II |
26 603,7 |
112,5 |
112,5 |
|||
2012 |
I |
10 896,3
|
- |
994,7 |
11,4 |
- |
1 006,1 |
II |
- |
1 312,5
|
- |
- |
1 312,5 |
||
2013 |
I |
- |
1 308,9
|
- |
- |
1 308,9 |
|
II |
3 409,1 |
1 316,1
|
- |
4 725,2 |
|||
2014 |
I |
3 409,1
|
1 189,9 |
- |
4 599,0 |
||
II |
3 409,1
|
1 076,8 |
- |
- |
4 485,9 |
||
2015 |
I |
3 409,1
|
951,9 |
- |
- |
4 361,0 |
|
II |
3 409,1
|
837,5 |
- |
- |
4 246,6 |
||
2016 |
I |
3 409,1
|
717,9 |
- |
- |
4 127,0 |
|
II |
3 409,1
|
598,2 |
- |
- |
4 007,3 |
||
2017 |
I |
3 409,1
|
476,0 |
- |
- |
3 885,1 |
|
II |
3 409,1
|
358,9 |
- |
- |
3 768,0 |
||
2018 |
I |
3 409,1
|
238,0 |
- |
- |
3 647,1 |
|
II |
3 409,1
|
119,6 |
- |
- |
3 528,7 |
||
Itogo:
|
37 500,0 |
37 500,0 |
11 497,0 |
11,4 |
112,5 |
49 120,9 |
Primechaniya:
*) Data pogasheniya osnovnogo dolga zavisit ot dati vstupleniya v silu kreditnogo dogovora i dati pervoy viborki.
**) Summi komissiy i protsentniх platejey zavisyat ot fakticheskiх summ i dat viborok.