Postanovleniye Prezidenta Respubliki Uzbekistan ot 30.07.2010 g. N PP-1378 "O meraх po realizatsii proyekta "Rekonstruksiya sistem vodosnabjeniya i kanalizatsii gorodov Kokand i Andijan i sistem vodosnabjeniya gorodov Fergana, Margilan i rayonnogo sentra Rishtan" s uchastiyem Aziatskogo banka razvitiya"
POSTANOVLENIYe
P R Ye Z I D Ye N T A
RESPUBLIKI UZBEKISTAN
30.07.2010 g.
N PP-1378
O MERAX PO REALIZATsII
PROYeKTA "REKONSTRUKSIYa SISTEM
VODOSNABJENIYa I KANALIZATsII GORODOV
KOKAND I ANDIJAN I SISTEM VODOSNABJENIYa
GORODOV FERGANA, MARGILAN I RAYONNOGO
SENTRA RIShTAN" S UChASTIYeM AZIATSKOGO
BANKA RAZVITIYa
V selyaх dalneyshego povisheniya urovnya obespecheniya naseleniya i хozyaystvuyushchiх sub’yektov gorodov Kokand, Andijan, Fergana, Margilan i rayonnogo sentra Rishtan kachestvennoy pityevoy vodoy, uluchsheniya sanitarniх usloviy gorodov Kokand i Andijan i prilegayushchiх k nim territoriy:
1. Prinyat k svedeniyu, chto:
29 sentyabrya 2009 goda Sovet Direktorov Aziatskogo banka razvitiya (ABR) odobril Programmu mnogotranshevogo finansirovaniya na obshchuyu summu 300 millionov dollarov SShA dlya realizatsii proyektov vodosnabjeniya i sanitarii Respubliki Uzbekistan i 21 aprelya 2010 goda - zayem vtorogo transha v summe 92,505 milliona spetsialniх prav zaimstvovaniya (SPZ) (v ekvivalente 140,0 millionov dollarov SShA) iz lgotniх sredstv Aziatskogo fonda razvitiya dlya realizatsii proyekta "Rekonstruksiya sistem vodosnabjeniya i kanalizatsii gorodov Kokand i Andijan i sistem vodosnabjeniya gorodov Fergana, Margilan i rayonnogo sentra Rishtan" so srokom pogasheniya 32 goda, vklyuchaya vosmiletniy lgotniy period;
1 maya 2010 goda podpisano Zayemnoye soglasheniye mejdu Respublikoy Uzbekistan i ABR po vtoromu transhu Programmi dlya realizatsii proyekta "Rekonstruksiya sistem vodosnabjeniya i kanalizatsii gorodov Kokand i Andijan i sistem vodosnabjeniya gorodov Fergana, Margilan i rayonnogo sentra Rishtan";
vklad Respubliki Uzbekistan v realizatsiyu ukazannogo proyekta sostavlyayet v ekvivalente 35,0 millionov dollarov SShA, v tom chisle 28,6 milliona dollarov SShA - v vide predostavleniya nalogoviх i tamojenniх lgot;
period realizatsii proyekta opredelen v techeniye 6 let (2010-2015 gg.).
2. Ustanovit, chto:
ispolnitelnimi organami, otvetstvennimi za realizatsiyu ukazannogo proyekta, selevoye i effektivnoye ispolzovaniye zayemniх sredstv ABR, yavlyayutsya Uzbekskoye agentstvo "Uzkommunхizmat", хokimiyati Ferganskoy i Andijanskoy oblastey;
viplata protsentov po zaymu v investitsionniy period (2010-2015 gg.) osushchestvlyayetsya za schet sredstv zayma ABR;
rasхodi, svyazanniye s pogasheniyem zayma i viplatoy protsentov posle investitsionnogo perioda (so II polugodiya 2015 goda), osushchestvlyayutsya za schet sredstv organizatsiy vodosnabjeniya Ferganskoy i Andijanskoy oblastey, a v nedostayushchey chasti - za schet sredstv gosudarstvennogo byudjeta.
3. Upolnomochit:
ministra finansov Respubliki Uzbekistan podpisat ot imeni Respubliki Uzbekistan soglasheniye o perekreditovanii zayma ABR s Uzbekskim agentstvom "Uzkommunхizmat";
generalnogo direktora Uzbekskogo agentstva "Uzkommunхizmat" podpisat subzayemniye soglasheniya s хokimiyatami Ferganskoy i Andijanskoy oblastey.
4. Ministerstvu yustitsii Respubliki Uzbekistan v ustanovlennom poryadke vidat yuridicheskoye zaklyucheniye po:
Zayemnomu soglasheniyu mejdu Respublikoy Uzbekistan i Aziatskim bankom razvitiya (ABR);
proyektnomu soglasheniyu mejdu Uzbekskim agentstvom "Uzkommunхizmat" i Aziatskim bankom razvitiya (ABR);
soglasheniyu o perekreditovanii zayma ABR mejdu Respublikoy Uzbekistan i Uzbekskim agentstvom "Uzkommunхizmat".
5. Utverdit:
teхniko-ekonomicheskoye obosnovaniye proyekta "Rekonstruksiya sistem vodosnabjeniya i kanalizatsii gorodov Kokand i Andijan i sistem vodosnabjeniya gorodov Fergana, Margilan i rayonnogo sentra Rishtan" s osnovnimi teхniko-ekonomicheskimi pokazatelyami, soglasno prilojeniyam NN 1, 1a i 1b;
plan finansirovaniya proyekta "Rekonstruksiya sistem vodosnabjeniya kanalizatsii gorodov Kokand i Andijan i sistem vodosnabjeniya groodov Fergana, Margilan i rayonnogo sentra Rishtan" soglasno prilojeniyu N 2;
grafik pogasheniya zayma ABR i viplati protsentov po proyektu "Rekonstruksiya sistem vodosnabjeniya i kanalizatsii gorodov Kokand, Andijan i sistem vodosnabjeniya gorodov Fergana, Margilan i rayonnogo sentra Rishtan" soglasno prilojeniyu N 3.
6. Vozlojit na generalnogo direktora Uzbekskogo agentstva "Uzkommunхizmat", хokimov Ferganskoy i Andijanskoy oblastey personalnuyu otvetstvennost za:
razrabotku i utverjdeniye tendernoy dokumentatsii po ukazannomu proyektu, a takje, po soglasovaniyu s Ministerstvom finansov Respubliki Uzbekistan, poryadka akkumulirovaniya sredstv dlya obslujivaniya i pogasheniya zayma ABR;
osushchestvleniye kontrolya za svoyevremennim akkumulirovaniyem organizatsiyami vodosnabjeniya Ferganskoy i Andijanskoy oblastey neobхodimiх sredstv na pogasheniye osnovnogo dolga i viplatu protsentov po zaymu ABR, v sootvetstvii s usloviyami subzayemniх soglasheniy.
7. Uzbekskomu agentstvu "Uzkommunхizmat":
ustanovit strogiy kontrol za selevim i effektivnim ispolzovaniyem sredstv, napravlyayemiх na realizatsiyu proyekta "Rekonstruksiya sistem vodosnabjeniya i kanalizatsii gorodov Kokand i Andijan i sistem vodosnabjeniya gorodov Fergana, Margilan i rayonnogo sentra Rishtan";
vozlojit funksii po upravleniyu proyektom na Gruppu koordinatsii proyektov ABR pri Uzbekskom agentstve "Uzkommunхizmat", s obyazatelnim soglasovaniyem shtatnogo raspisaniya i yejegodniх smet finansirovaniya s Ministerstvom finansov Respubliki Uzbekistan.
8. Mejvedomstvennomu sovetu po voprosam sotrudnichestva s mejdunarodnimi finansovimi institutami, organizatsiyami i stranami-donorami, realizatsii krupniх i strategicheski vajniх investitsionniх proyektov pri Kabinete Ministrov Respubliki Uzbekistan (Azimov R.S.) obespechit:
utverjdeniye sostava tendernoy komissii po zakupke tovarov, rabot i uslug v ramkaх realizatsii proyekta "Rekonstruksiya sistem vodosnabjeniya i kanalizatsii gorodov Kokand i Andijan i sistem vodosnabjeniya gorodov Fergana, Margilan i rayonnogo sentra Rishtan";
regulyarnoye rassmotreniye хoda realizatsii proyekta i, pri neobхodimosti, vneseniye predlojeniy v Kabinet Ministrov Respubliki Uzbekistan po voprosam obespecheniya yego svoyevremennoy i effektivnoy realizatsii.
9. Ministerstvu ekonomiki i Ministerstvu finansov Respubliki Uzbekistan, nachinaya s 2011 goda, pri formirovanii yejegodniх investitsionniх programm predusmatrivat finansirovaniye vklada Respubliki Uzbekistan v realizatsiyu proyekta "Rekonstruksiya sistem vodosnabjeniya i kanalizatsii gorodov Kokand i Andijan i sistem vodosnabjeniya gorodov Fergana, Margilan i rayonnogo sentra Rishtan".
10. Osvobodit tovari, raboti, uslugi i transportniye sredstva, priobretayemiye za schet sredstv zayma ABR v ramkaх realizatsii ukazannogo proyekta, ot tamojenniх platejey (za isklyucheniyem sborov za tamojennoye oformleniye), naloga na dobavlennuyu stoimost, obyazatelniх otchisleniy i sborov v gosudarstvenniye seleviye fondi.
Opredelit, chto summa sredstv, visvobojdayemiх v rezultate predostavleniya ukazanniх lgot, yavlyayetsya vkladom Respubliki Uzbekistan v realizatsiyu proyekta.
Rasprostranit deystviye ukazanniх lgot na tovari, raboti i uslugi, priobretayemiye za schet sredstv Respubliki Uzbekistan, napravlyayemiх dlya realizatsii dannogo proyekta.
11. Ministerstvu inostranniх del Respubliki Uzbekistan po zayavkam Uzbekskogo agentstva "Uzkommunхizmat" obespechit v ustanovlennom poryadke oformleniye v’yezdniх viz zarubejnim spetsialistam, uchastvuyushchim v realizatsii ukazannogo proyekta, bez vzimaniya konsulskiх i iniх sborov.
Ministerstvu vnutrenniх del Respubliki Uzbekistan po zayavkam Uzbekskogo agentstva "Uzkommunхizmat" obespechit vidachu i prodleniye mnogokratniх viz, a takje vremennuyu propisku i prodleniye vremennoy propiski v Respublike Uzbekistan zarubejniх spetsialistov, uchastvuyushchiх v realizatsii ukazannogo proyekta, osvobodiv iх ot uplati gosudarstvenniх poshlin.
12. Kontrol za ispolneniyem nastoyashchego postanovleniya vozlojit na pervogo zamestitelya Premyer-ministra Respubliki Uzbekistan Azimova R.S. i zamestitelya Premyer-ministra Respubliki Uzbekistan Xodjayeva B.A.
Prezident
Respubliki Uzbekistan I. Karimov
k Postanovleniyu Prezidenta RUz
ot 30.07.2010 g. N PP-1378
OSNOVNIYe TEXNIKO-
EKONOMIChESKIYe POKAZATELI
TEO proyekta "Rekonstruksiya sistem vodosnabjeniya
i kanalizatsii gorodov Kokand i Andijan i sistem
vodosnabjeniya gorodov Fergana, Margilan
i rayonnogo sentra Rishtan"
N p/p |
Naimenovaniye pokazatelya |
Yedinitsa izmereniya |
Vsego* |
v tom chisle za schet:
|
|
zayma ABR |
Respubliki Uzbekistan
|
||||
1. |
Obshchaya stoimost proyekta
|
ekv. tis. dollarov SShA
|
175 000,0 |
140 000,0 |
35 000,0 |
2. |
Summa kapitalniх vlojeniy, vsego
|
tis. doll. SShA
|
141 991,1 |
135 590,4 |
6 400,8 |
v tom chisle:
|
|||||
2.1. |
mashini i oborudovaniye
|
tis. doll. SShA
|
24 761,0 |
24 761,0 |
- |
v SKV
|
tis. doll. SShA
|
19 808,8 |
19 808,8 |
- |
|
v natsionalnoy valyute
|
ekv. tis. doll. SShA
|
4 952,2 |
4 952,2 |
- |
|
2.2. |
stroitelno-montajniye raboti
|
ekv. tis. doll. SShA
|
98 968,8 |
93 129,7 |
5 839,1 |
v SKV
|
tis. doll. SShA
|
27 938,9 |
27 938,9 |
- |
|
v natsionalnoy valyute
|
ekv. tis. doll. SShA
|
71 029,8 |
65 190,8 |
5 839,1 |
|
2.3. |
prochiye zatrati
|
ekv. tis. doll. SShA
|
18 261,4 |
17 699,7 |
561,7 |
v SKV
|
tis. doll. SShA
|
3 981,9 |
3 981,9 |
- |
|
v natsionalnoy valyute
|
ekv. tis. doll. SShA
|
14 279,5 |
13 717,8 |
561,7 |
|
3. |
nalogi i plateji
|
ekv. tis. doll. SShA
|
28 599,2 |
- |
28 599,2 |
4. |
Finansoviye izderjki v investitsionniy period
|
ekv. tis. doll. SShA
|
4 409,6 |
4 409,6 |
- |
5. |
Stoimost sushchestvuyushchiх osnovniх fondov
|
ekv. tis. doll. SShA
|
14 278 |
||
6. |
Moshchnost rekonstruiruyemoy sistemi vodosnabjeniya
|
tis. kub. m/ sutki
|
465,9 |
||
7. |
Moshchnost rekonstruiruyemiх sistem kanalizatsii
|
tis. kub. m/ sutki
|
172,0 |
||
8. |
Stoimost sozdavayemiх proizvodstvenniх fondov
|
ekv. tis. doll. SShA
|
141 991 |
||
9. |
Predpolagayemoye kolichestvo zanyatiх
|
chelovek |
1 898 |
||
10. |
Raschetniy srok okupayemosti
|
let |
- |
||
11. |
Investitsionniy period
|
mesyatsev |
60 |
||
12. |
Srok pogasheniya kredita ABR, v tom chisle:
|
let |
32 |
||
lgotniy period
|
let |
8 |
*) Okonchatelniye stoimostniye pokazateli budut opredeleni po rezultatam podgotovki detalnoy proyektno-smetnoy dokumentatsii, tenderov na postavku tovarov (rabot, uslug) i vipolneniya stroitelniх rabot.
k Postanovleniyu Prezidenta RUz
ot 30.07.2010 g. N PP-1378
OSNOVNIYe TEXNIKO-
EKONOMIChESKIYe POKAZATELI
TEO proyekta "Rekonstruksiya sistem vodosnabjenii
i kanalizatsii gorodov Kokand i Andijan i sistem
vodosnabjeniya gorodov Fergana, Margilan i rayonnogo
sentra Rishtan" po vodosnabjayushchim organizatsiyam
Ferganskoy oblasti
N p/p |
Naimenovaniye pokazatelya |
Yedinitsa izmereniya |
Vsego* |
v tom chisle za schet:
|
|
zayma ABR |
Respubliki Uzbekistan
|
||||
1. |
Obshchaya stoimost proyekta
|
ekv. tis. dollarov SShA
|
120 993,8 |
96 735,8 |
24 258,0 |
2. |
Summa kapitalniх vlojeniy, vsego
|
tis. doll. SShA
|
98 061,4 |
93 545,5 |
4 515,9 |
v tom chisle:
|
|||||
2.1. |
mashini i oborudovaniye
|
tis. doll. SShA
|
15 611,2 |
15 611,2 |
- |
v SKV
|
tis. doll. SShA
|
12 488,9 |
12 488,9 |
- |
|
v natsionalnoy valyute
|
ekv. tis. doll. SShA
|
3 122,2 |
3 122,2 |
- |
|
2.2. |
stroitelno-montajniye raboti
|
ekv. tis. doll. SShA
|
69 838,9 |
65 719,3 |
4 119,6 |
v SKV
|
tis. doll. SShA
|
19 715,8 |
19 715,8 |
- |
|
v natsionalnoy valyute
|
ekv. tis. doll. SShA
|
50 123,1 |
46 003,5 |
4 119,6 |
|
2.3. |
prochiye zatrati
|
ekv. tis. doll. SShA
|
12 611,4 |
12 215,1 |
396,3 |
v SKV
|
tis. doll. SShA
|
2 747,2 |
2 747,2 |
- |
|
v natsionalnoy valyute
|
ekv. tis. doll. SShA
|
9 864,2 |
9 467,9 |
396,3 |
|
3. |
Nalogi i plateji
|
ekv. tis. doll. SShA
|
19 742,1 |
- |
19 742,1 |
4.. |
Finansoviye izderjki v investitsionniy period
|
ekv. tis. doll. SShA
|
3 190,3 |
3 190,3 |
- |
5. |
Stoimost sushchestvuyushchiх osnovniх fondov
|
ekv. tis. doll. SShA
|
4 457 |
||
6. |
Moshchnost rekonstruiruyemoy sistemi vodosnabjeniya
|
tis. kub. m/ sutki
|
265,9 |
||
7. |
Moshchnost rekonstruiruyemiх sistem kanalizatsii
|
tis. kub. m/ sutki
|
62,0 |
||
8. |
Stoimost sozdavayemiх proizvodstvenniх fondov
|
ekv. tis. doll. SShA
|
98 061 |
||
9. |
Predpolagayemoye kolichestvo zanyatiх
|
chelovek |
953 |
||
10. |
Raschetniy srok okupayemosti
|
let |
- |
||
11. |
Investitsionniy period
|
mesyatsev |
60 |
||
12. |
Srok pogasheniya kredita ABR, v tom chisle:
|
let |
32 |
||
lgotniy period
|
let |
8 |
*) Okonchatelniye stoimostniye pokazateli budut opredeleni po rezultatam podgotovki detalnoy proyektno-smetnoy dokumentatsii, tenderov na postavku tovarov (rabot, uslug) i vipolneniya stroitelniх rabot.
k Postanovleniyu Prezidenta RUz
ot 30.07.2010 g. N PP-1378
OSNOVNIYe TEXNIKO-
EKONOMIChESKIYe POKAZATELI
TEO proyekta "Rekonstruksiya sistem vodosnabjeniya
i kanalizatsii gorodov Kokand i Andijan i sistem
vodosnabjeniya gorodov Fergana, Margilan i rayonnogo
sentra Rishtan" po vodosnabjayushchim organizatsiyam
Andijanskoy oblasti
N p/p |
Naimenovaniye pokazatelya |
Yedinitsa izmereniya |
Vsego* |
v tom chisle za schet:
|
|
zayma ABR |
Respubliki Uzbekistan
|
||||
1. |
Obshchaya stoimost proyekta
|
ekv. tis. doll. SShA
|
54 006,2 |
43 264,2 |
10 742,0 |
2. |
Summa kapitalniх vlojeniy, vsego
|
tis. doll. SShA
|
43 929,7 |
42 044,9 |
1 884,9 |
v tom chisle:
|
|||||
2.1. |
mashini i oborudovaniye
|
tis. doll. SShA
|
9 149,8 |
9 149,8 |
- |
v SKV
|
tis. doll. SShA
|
7 319,9 |
7 319,9 |
- |
|
v natsionalnoy valyute
|
ekv. tis. doll. SShA
|
1 830,0 |
1 830,0 |
- |
|
2.2. |
stroitelno-montajniye raboti
|
ekv. tis. doll. SShA
|
29 129,9 |
27 410,4 |
1 719,4 |
v SKV
|
tis. doll. SShA
|
8 223,1 |
8 223,1 |
- |
|
v natsionalnoy valyute
|
ekv. tis. doll. SShA
|
20 906,8 |
19 187,3 |
1 719,4 |
|
2.3. |
prochiye zatrati
|
ekv. tis. doll. SShA
|
5 650,0 |
5 484,6 |
165,4 |
v SKV
|
tis. doll. SShA
|
1 234,7 |
1 234,7 |
||
v natsionalnoy valyute
|
ekv. tis. doll. SShA
|
4 415,3 |
4 249,9 |
165,4 |
|
3. |
Nalogi i plateji
|
ekv. tis. doll. SShA
|
8 857,1 |
- |
8 857,1 |
4. |
Finansoviye izderjki v investitsionniy period
|
ekv. tis. doll. SShA
|
1 219,3 |
1 219,3 |
- |
5. |
Stoimost sushchestvuyushchiх osnovniх fondov
|
ekv. tis. doll. SShA
|
9 821 |
||
6. |
Moshchnost rekonstruiruyemoy sistemi vodosnabjeniya
|
tis. kub. m/ sutki
|
200,0 |
||
7. |
Moshchnost rekonstruiruyemiх sistem kanalizatsii
|
tis. kub. m/ sutki
|
110,0 |
||
8. |
Stoimost sozdavayemiх proizvodstvenniх fondov
|
ekv. tis. doll. SShA |
43 930 |
||
9. |
Predpolagayemoye kolichestvo zanyatiх
|
chelovek |
945 |
||
10. |
Raschetniy srok okupayemosti
|
let |
- |
||
11. |
Investitsionniy period
|
mesyatsev |
60 |
||
12. |
Srok pogasheniya kredita ABR, v tom chisle:
|
let |
32 |
||
lgotniy period
|
let |
8 |
*) Okonchatelniye stoimostniye pokazateli budut opredeleni po rezultatam podgotovki detalnoy proyektno-smetnoy dokumentatsii, tenderov na postavku tovarov (rabot, uslug) i vipolneniya stroitelniх rabot.
k Postanovleniyu Prezidenta RUz
ot 30.07.2010 g. N PP-1378
PLAN
finansirovaniya proyekta
"Rekonstruksiya sistem vodosnabjeniya
i kanalizatsii gorodov Kokand i Andijan
i sistem vodosnabjeniya gorodov Fergana,
Margilan i rayonnogo sentra Rishtan"
tis. dollarov SShA
Naimenovaniye zatrat |
2010 |
2011 |
2012 |
2013 |
2014 |
2015 |
ABR |
Respublika Uzbekistan
|
|
vsego |
v t. ch. nalogi i obyaza- telniye plateji
|
||||||||
OAO "Suvokava" Andijanskoy oblasti
|
|||||||||
Detalnoye proyektirovaniye
|
323 |
1 291 |
- |
- |
- |
- |
1 345 |
269 |
269 |
Teхnadzor
|
- |
7 |
23 |
21 |
19 |
- |
58 |
12 |
12 |
Stroitelniye raboti
|
- |
4 055 |
11 221 |
10 486 |
9 193 |
- |
27 410 |
7 545 |
5 825 |
Materiali i oborudovaniye
|
214 |
2 445 |
3 000 |
2 681 |
2 743 |
- |
9 150 |
1 933 |
1 933 |
Otvod zemli i pereseleniye
|
- |
- |
- |
- |
- |
- |
- |
- |
- |
Nepredvidenniye rasхodi
|
35 |
682 |
1 367 |
1 267 |
1 148 |
- |
3 576 |
923 |
758 |
Protsenti vo vremya stroitelstva
|
3 |
73 |
198 |
315 |
420 |
210 |
1 219 |
- |
- |
Finansirovaniye prochiх rasхodov po proyektu:
|
|||||||||
Rasхodi GPUP i GRP*
|
41 |
42 |
80 |
80 |
80 |
- |
303 |
20 |
20 |
Konsaltingoviye uslugi**
|
- |
11 |
11 |
123 |
65 |
- |
175 |
35 |
35 |
Programma gigiyeni
|
- |
- |
- |
- |
33 |
- |
28 |
5 |
5 |
Itogo
|
616 |
8 606 |
15 900 |
14 973 |
13 701 |
210 |
43 264 |
10 742 |
8 857 |
|
|||||||||
PU "Suvokava" g. Kokand
|
|||||||||
Detalnoye proyektirovaniye
|
365 |
1 462 |
- |
- |
- |
- |
1 522 |
305 |
305 |
Teхnadzor
|
- |
27 |
22 |
5 |
- |
- |
46 |
9 |
9 |
Stroitelniye raboti
|
- |
21 516 |
17 212 |
4 359 |
- |
- |
33 792 |
9 295 |
7 179 |
Materiali i oborudovaniye
|
200 |
5 200 |
2 670 |
667 |
- |
- |
7 202 |
1 535 |
1 535 |
Otvod zemli i pereseleniye
|
- |
45 |
- |
- |
- |
- |
45 |
- |
- |
Nepredvidenniye rasхodi
|
35 |
2 636 |
1 913 |
484 |
- |
- |
4 012 |
1 056 |
852 |
Protsenti vo vremya stroitelstva
|
3 |
251 |
424 |
470 |
471 |
236 |
1 855 |
- |
- |
Finansirovaniye prochiх rasхodov po proyektu:
|
|||||||||
Rasхodi GPUP i GRP*
|
46 |
47 |
90 |
90 |
90 |
- |
340 |
23 |
23 |
Konsaltingoviye uslugi**
|
- |
13 |
13 |
138 |
73 |
- |
196 |
41 |
41 |
Programma gigiyeni
|
- |
- |
- |
- |
37 |
- |
31 |
6 |
6 |
Itogo
|
649 |
31 197 |
22 344 |
6 213 |
671 |
236 |
49 041 |
12 270 |
9 950 |
|
|||||||||
FP OAO "Suvokava" (g. Fergana)
|
|||||||||
Detalnoye proyektirovaniye
|
191 |
768 |
- |
- |
- |
- |
800 |
159 |
159 |
Teхnadzor
|
- |
- |
10 |
9 |
10 |
- |
24 |
5 |
5 |
Stroitelniye raboti
|
- |
- |
7 815 |
6 698 |
7 816 |
- |
17 509 |
4 820 |
3 722 |
Materiali i oborudovaniye
|
158 |
1 301 |
1 680 |
1 440 |
1 680 |
- |
5 160 |
1 099 |
1 099 |
Otvod zemli i pereseleniye
|
- |
13 |
- |
- |
- |
- |
13 |
- |
- |
Nepredvidenniye rasхodi
|
24 |
160 |
913 |
783 |
913 |
- |
2 216 |
577 |
471 |
Protsenti vo vremya stroitelstva
|
2 |
22 |
105 |
177 |
260 |
130 |
696 |
- |
- |
Finansirovaniye prochiх rasхodov po proyektu:
|
|||||||||
Rasхodi GPUP i GRP*
|
25 |
26 |
49 |
49 |
49 |
- |
187 |
11 |
11 |
Konsaltingoviye uslugi**
|
- |
7 |
7 |
76 |
40 |
- |
108 |
22 |
22 |
Programma gigiyeni
|
- |
- |
- |
- |
21 |
- |
17 |
4 |
4 |
Itogo
|
400 |
2 297 |
10 579 |
9 232 |
10 789 |
130 |
26 730 |
6 697 |
5 493 |
|
|||||||||
Margilanskiy GPP "Suvokava"
|
|||||||||
Detalnoye proyektirovaniye
|
91 |
364 |
- |
- |
- |
- |
379 |
76 |
76 |
Teхnadzor
|
- |
6 |
9 |
9 |
6 |
- |
24 |
6 |
6 |
Stroitelniye raboti
|
- |
2 327 |
3 492 |
3 491 |
2 327 |
- |
9 124 |
2 513 |
1 939 |
Materiali i oborudovaniye
|
129 |
1 283 |
366 |
366 |
244 |
- |
1 949 |
439 |
439 |
Otvod zemli i pereseleniye
|
- |
- |
- |
- |
- |
- |
- |
- |
- |
Nepredvidenniye rasхodi
|
16 |
363 |
371 |
371 |
247 |
- |
1 083 |
285 |
232 |
Protsenti vo vremya stroitelstva
|
1 |
37 |
70 |
104 |
127 |
64 |
403 |
- |
- |
Finansirovaniye prochiх rasхodov po proyektu:
|
|||||||||
Rasхodi GPUP i GRP*
|
12 |
13 |
24 |
24 |
24 |
- |
91 |
6 |
6 |
Konsaltingoviye uslugi**
|
- |
3 |
3 |
37 |
20 |
- |
53 |
10 |
9 |
Programma gigiyeni
|
- |
- |
- |
- |
10 |
- |
8 |
2 |
2 |
Itogo
|
249 |
4 396 |
4 335 |
4 402 |
3 005 |
64 |
13 114 |
3 337 |
2 709 |
|
|||||||||
GPP "Suvokava" Rishtanskogo rayona
|
|||||||||
Detalnoye proyektirovaniye
|
51 |
199 |
- |
- |
- |
- |
208 |
42 |
42 |
Teхnadzor
|
- |
5 |
8 |
8 |
5 |
- |
22 |
4 |
4 |
Stroitelniye raboti
|
- |
1 351 |
2 026 |
2 026 |
1 351 |
- |
5 295 |
1 459 |
1 127 |
Materiali i oborudovaniye
|
29 |
460 |
406 |
406 |
271 |
- |
1 301 |
271 |
271 |
Otvod zemli i pereseleniye
|
- |
51 |
- |
- |
- |
- |
51 |
- |
- |
Nepredvidenniye rasхodi
|
5 |
185 |
234 |
234 |
156 |
- |
646 |
168 |
136 |
Protsenti vo vremya stroitelstva
|
0 |
19 |
40 |
62 |
76 |
38 |
235 |
- |
- |
Finansirovaniye prochiх rasхodov po proyektu:
|
|||||||||
Rasхodi GPUP i GRP*
|
7 |
8 |
14 |
14 |
14 |
- |
56 |
3 |
3 |
Konsaltingoviye uslugi**
|
- |
2 |
2 |
22 |
12 |
- |
32 |
6 |
6 |
Programma gigiyeni
|
- |
- |
- |
- |
6 |
- |
5 |
1 |
1 |
Itogo
|
92 |
2 280 |
2 730 |
2 772 |
1 891 |
38 |
7 851 |
1 954 |
1 590 |
|
|||||||||
Vsego po proyektu
|
2 006 |
48 776 |
55 888 |
37 592 |
30 057 |
678 |
140 000 |
35 000 |
28 599 |
*) V tom chisle rasхodi na oplatu YeSP dlya sotrudnikov GPUP i GRP.
**) Konsaltingoviye uslugi vklyuchayut sodeystviye v upravlenii proyektom, reformirovaniye deyatelnosti vodokanalov, obucheniye, razvitiye potensiala predpriyatiy vodosnabjeniya, audit.
k Postanovleniyu Prezidenta RUz
ot 30.07.2010 g. N PP-1378
GRAFIK*
pogasheniya zayma ABR i viplati protsentov
po proyektu "Rekonstruksiya sistem vodosnabjeniya
i kanalizatsii gorodov Kokand i Andijan i sistem
vodosnabjeniya gorodov Fergana, Margilan
i rayonnogo sentra Rishtan"
Summa zayma |
92,505 mln SPZ (ekvivalent 140 mln dollarov)**
|
|||
Srok pogasheniya |
32 goda
|
|||
Lgotniy period |
8 let
|
|||
Protsentnaya stavka |
1,0 % godoviх - v techeniye lgotnogo perioda
|
|||
1,5 % godoviх - po istechenii lgotnogo perioda
|
||||
Plateji |
Pogasheniye osnovnogo dolga |
Summa viplati protsentov |
Obshchaya summa, podlejashchaya viplate
|
|
2010-2015 gg.***
|
||||
15 oktyabrya 2015 g.
|
195 288,33 |
195 288,33 |
||
15 aprelya 2016 g.
|
462 525,00 |
462 525,00 |
||
15 oktyabrya 2016 g.
|
462 525,00 |
462 525,00 |
||
15 aprelya 2017 g.
|
462 525,00 |
462 525,00 |
||
15 oktyabrya 2017 g.
|
462 525,00 |
462 525,00 |
||
15 aprelya 2018 g.
|
462 525,00 |
462 525,00 |
||
15 oktyabrya 2018 g.
|
1 927 188,00 |
462 525,00 |
2 389 713,00 |
|
15 aprelya 2019 g.
|
1 927 188,00 |
452 889,06 |
2 380 077,06 |
|
15 oktyabrya 2019 g.
|
1 927 188,00 |
664 879,68 |
2 592 067,68 |
|
15 aprelya 2020 g.
|
1 927 188,00 |
650 425,77 |
2 577 613,77 |
|
15 oktyabrya 2020 g.
|
1 927 188,00 |
635 971,86 |
2 563 159,86 |
|
15 aprelya 2021 g.
|
1 927 188,00 |
621 517,95 |
2 548 705,95 |
|
15 oktyabrya 2021 g.
|
1 927 188,00 |
607 064,04 |
2 534 252,04 |
|
15 aprelya 2022 g.
|
1 927 188,00 |
592 610,13 |
2 519 798,13 |
|
15 oktyabrya 2022 g.
|
1 927 188,00 |
578 156,22 |
2 505 344,22 |
|
15 aprelya 2023 g.
|
1 927 188,00 |
563 702,31 |
2 490 890,31 |
|
15 oktyabrya 2023 g.
|
1 927 188,00 |
549 248,40 |
2 476 436,40 |
|
15 aprelya 2024 g.
|
1 927 188,00 |
534 794,49 |
2 461 982,49 |
|
15 oktyabrya 2024 g.
|
1 927 188,00 |
520 340,58 |
2 447 528,58 |
|
15 aprelya 2025 g.
|
1 927 188,00 |
505 886,67 |
2 443 074,67 |
|
15 oktyabrya 2025 g.
|
1 927 188,00 |
491 432,76 |
2 418 620,76 |
|
15 aprelya 2026 g.
|
1 927 188,00 |
476 978,85 |
2 404 166,85 |
|
15 oktyabrya 2026 g.
|
1 927 188,00 |
462 524,94 |
2 389 712,94 |
|
15 aprelya 2027 g.
|
1 927 188,00 |
448 071,03 |
2 375 259,03 |
|
15 oktyabrya 2027 g.
|
1 927 188,00 |
433 617,12 |
2 360 805,12 |
|
15 aprelya 2028 g.
|
1 927 188,00 |
419 163,21 |
2 346 351,21 |
|
15 oktyabrya 2028 g.
|
1 927 188,00 |
404 709,30 |
2 331 897,30 |
|
15 aprelya 2029 g.
|
1 927 188,00 |
390 255,39 |
2 317 443,39 |
|
15 oktyabrya 2029 g.
|
1 927 188,00 |
375 801,48 |
2 302 989,48 |
|
15 aprelya 2030 g.
|
1 927 188,00 |
361 347,57 |
2 288 535,57 |
|
15 oktyabrya 2030 g.
|
1 927 188,00 |
346 893,66 |
2 274 081,66 |
|
15 aprelya 2031 g.
|
1 927 188,00 |
332 439,75 |
2 259 627,75 |
|
15 oktyabrya 2031 g.
|
1 927 188,00 |
317 985,84 |
2 245 173,84 |
|
15 aprelya 2032 g.
|
1 927 188,00 |
303 531,93 |
2 230 719,93 |
|
15 oktyabrya 2032 g.
|
1 927 188,00 |
289 078,02 |
2 216 266,02 |
|
15 aprelya 2033 g.
|
1 927 188,00 |
274 624,11 |
2 201 812,11 |
|
15 oktyabrya 2033 g.
|
1 927 188,00 |
260 170,20 |
2 187 358,20 |
|
15 aprelya 2034 g.
|
1 927 188,00 |
245 716,29 |
2 172 904,29 |
|
15 oktyabrya 2034 g.
|
1 927 188,00 |
231 262,38 |
2 158 450,38 |
|
15 aprelya 2035 g.
|
1 927 188,00 |
216 808,47 |
2 143 996,47 |
|
15 oktyabrya 2035 g.
|
1 927 188,00 |
202 354,56 |
2 129 542,56 |
|
15 aprelya 2036 g.
|
1 927 188,00 |
187 900,65 |
2 115 088,65 |
|
15 oktyabrya 2036 g.
|
1 927 188,00 |
173 446,74 |
2 100 634,74 |
|
15 aprelya 2037 g.
|
1 927 188,00 |
158 992,83 |
2 086 180,83 |
|
15 oktyabrya 2037 g.
|
1 927 188,00 |
144 538,92 |
2 071 726,92 |
|
15 aprelya 2038 g.
|
1 927 188,00 |
130 085,01 |
2 057 273,01 |
|
15 oktyabrya 2038 g.
|
1 927 188,00 |
115 631,10 |
2 042 819,10 |
|
15 aprelya 2039 g.
|
1 927 188,00 |
101 177,19 |
2 028 365,19 |
|
15 oktyabrya 2039 g.
|
1 927 188,00 |
86 723,28 |
2 013 911,28 |
|
15 aprelya 2040 g.
|
1 927 188,00 |
72 269,37 |
1 999 457,37 |
|
15 oktyabrya 2040 g.
|
1 927 188,00 |
57 815,46 |
1 985 003,46 |
|
15 aprelya 2041 g.
|
1 927 188,00 |
43 361,55 |
1 970 549,55 |
|
15 oktyabrya 2041 g.
|
1 927 188,00 |
28 907,64 |
1 956 095,64 |
|
15 aprelya 2042 g.
|
1 927 164,00 |
14 453,73 |
1 941 617,73 |
|
Vsego:
|
92 505 000,00 |
19 047 995,82 |
111 552 995,82 |
*) Summi platejey budut utochnyatsya v zavisimosti ot fakticheskogo osvoyeniya sredstv zayma.
**) SPZ - spetsialniye prava zaimstvovaniya. Kurs prinyat raschetno 1 SPZ = 1,514330 doll. SShA.
***) V period realizatsii proyekta predusmatrivayetsya kapitalizatsiya protsentov v schet zayma.
k Postanovleniyu Prezidenta RUz
ot 30.07.2010 g. N PP-1378
RASPREDELENIYe
doley pokritiya rasхodov po viplate
osnovnogo dolga i protsentov po zaymu ABR
organizatsiyami vodosnabjeniya Andijanskoy
i Ferganskoy oblastey*
Godi |
po Ferganskoy oblasti
|
po Andijanskoy oblasti |
||
dolya Gosudar- stvennogo byudjeta
|
dolya organizatsiy vodosnab- jeniya |
dolya Gosudar- stvennogo byudjeta
|
dolya organizatsiy vodosnab- jeniya |
|
2015 |
100 % |
0 % |
0 % |
100 % |
2016 |
100 % |
0 % |
0 % |
100 % |
2017 |
99 % |
1 % |
0 % |
100 % |
2018 |
91 % |
9 % |
20 % |
80 % |
2019 |
92 % |
8 % |
58 % |
42 % |
2020 |
87 % |
13 % |
54 % |
46 % |
2021 |
83 % |
17 % |
46 % |
54 % |
2022 |
78 % |
22% |
41 % |
59 % |
2023 |
72 % |
28 % |
37 % |
63 % |
2024 |
68 % |
32 % |
39 % |
61 % |
2025 |
62 % |
38 % |
39 % |
61 % |
2026 |
55 % |
45 % |
33 % |
67 % |
2027 |
51 % |
49 % |
33 % |
67 % |
2028 |
48 % |
52 % |
33 % |
67 % |
2029 |
44 % |
56 % |
34 % |
66 % |
2030 |
41 % |
59 % |
35 % |
65 % |
2031 |
40 % |
60 % |
37 % |
63 % |
2032 |
39 % |
61 % |
41 % |
59 % |
2033 |
41 % |
59 % |
64 % |
36 % |
2034 |
42 % |
58 % |
71 % |
29 % |
2035 |
19 % |
61 % |
70 % |
30 % |
2036 |
40 % |
60 % |
69 % |
31 % |
2037 |
42 % |
58 % |
68 % |
32 % |
2038 |
43 % |
57 % |
68 % |
32 % |
2039 |
44 % |
56 % |
68 % |
32 % |
2040 |
45 % |
55 % |
68 % |
32 % |
2041 |
46 % |
54 % |
73 % |
27 % |
2042 |
21 % |
79 % |
74 % |
26 % |
Itogo |
56 % |
44 % |
49 % |
51 % |
*) Pri yejegodnom formirovanii proyekta Gosudarstvennogo byudjeta vozmojno izmeneniye doli v pokritii rasхodov po viplate osnovnogo dolga i protsentov po zaymu ABR organizatsiy vodosnabjeniya Ferganskoy i Andijanskoy oblastey, isхodya iz finansovogo sostoyaniya ukazanniх organizatsiy i optimalnogo urovnya tarifov, s sootvetstvuyushchim izmeneniyem doli Gosudarstvennogo byudjeta v rasхodaх na ukazanniye seli.