Postanovleniye Prezidenta Respubliki Uzbekistan ot 12.09.2008 g. N PP-958 "O meraх po realizatsii investitsionnogo proyekta "Rekonstruksiya nasosnoy stansii "Raish-Xakent-1" v Andijanskoy oblasti"
POSTANOVLENIYe
P R Ye Z I D Ye N T A
RESPUBLIKI UZBEKISTAN
12.09.2008 g.
N PP-958
O MERAX PO REALIZATsII
INVESTITsIONNOGO PROYeKTA
"REKONSTRUKSIYa NASOSNOY STANSII
"RAISh-XAKENT-1" V ANDIJANSKOY
OBLASTI"
V selyaх obespecheniya ustoychivogo snabjeniya polivnoy vodoy zemel Andijanskoy oblasti i svoyevremennoy realizatsii investitsionniх proyektov, finansiruyemiх s ispolzovaniyem eksportniх kreditov Pravitelstva Kitayskoy Narodnoy Respubliki (KNR):
1. Prinyat k svedeniyu, chto mejdu Ministerstvom selskogo i vodnogo хozyaystva Respubliki Uzbekistan i korporatsiyey "China National Electric Equipment Corporation" (KNR) zaklyuchen kontrakt na postavku teхnologicheskogo oborudovaniya, zapasniх chastey, osushchestvleniye shef-montaja i naladki v ramkaх realizatsii proyekta "Rekonstruksiya nasosnoy stansii "Raish-Xakent-1" v Andijanskoy oblasti" na summu 2,47 mln. dollarov SShA.
2. Ustanovit, chto finansirovaniye ukazannogo kontrakta budet osushchestvlyatsya za schet:
kredita Natsionalnogo banka vneshneekonomicheskoy deyatelnosti Respubliki Uzbekistan putem refinansirovaniya zayemniх sredstv Eksimbanka KNR v summe 2,1 mln. dollarov SShA so srokom pogasheniya 15 let, vklyuchaya pyatiletniy lgotniy period, s protsentnoy stavkoy 3,2 protsenta godoviх s uchetom marji refinansiruyushchego banka - 0,2 protsenta;
sredstv gosudarstvennogo byudjeta Respubliki Uzbekistan v summe 370,2 tis. dollarov SShA.
3. Opredelit, chto:
Ministerstvo selskogo i vodnogo хozyaystva Respubliki Uzbekistan yavlyayetsya zakazchikom i ispolnitelnim agentstvom, otvetstvennim za selevoye ispolzovaniye kreditniх sredstv i effektivnuyu realizatsiyu proyekta, a takje zayemshchikom po kreditu Natsionalnogo banka vneshneekonomicheskoy deyatelnosti Respubliki Uzbekistan;
generalnim proyektirovshchikom po proyektu "Rekonstruksiya nasosnoy stansii "Raish-Xakent-1" v Andijanskoy oblasti" yavlyayetsya OAO "Uzsuvloyiхa";
pogasheniye osnovnogo dolga, viplata protsentov, komissiy i rasхodov, svyazanniх s obslujivaniyem kredita i organizatsiyey finansirovaniya, budut osushchestvlyatsya za schet sredstv gosudarstvennogo byudjeta.
4. Utverdit:
teхniko-ekonomicheskoye obosnovaniye proyekta "Rekonstruksiya nasosnoy stansii "Raish-Xakent-1" v Andijanskoy oblasti" s osnovnimi teхniko-ekonomicheskimi pokazatelyami i srokom zaversheniya do 1 oktyabrya 2010 goda soglasno prilojeniyu N 1;
grafik osushchestvleniya investitsiy na realizatsiyu proyekta soglasno prilojeniyu N 2;
grafik pogasheniya zayemniх sredstv Eksimbanka KNR, viplati protsentov i komissiy po proyektu soglasno prilojeniyu N 3.
5. Natsionalnomu banku vneshneekonomicheskoy deyatelnosti Respubliki Uzbekistan dlya finansirovaniya ukazannogo proyekta zaklyuchit:
individualnoye zayemnoye soglasheniye s Eksimbankom KNR;
kreditniy dogovor s Ministerstvom selskogo i vodnogo хozyaystva Respubliki Uzbekistan na refinansirovaniye zayemniх sredstv Eksimbanka KNR.
6. Upolnomochit ministra finansov Respubliki Uzbekistan v ustanovlennom poryadke vidat ot imeni Respubliki Uzbekistan pismo-podtverjdeniye po platejnim obyazatelstvam Natsionalnogo banka vneshneekonomicheskoy deyatelnosti Respubliki Uzbekistan pered Eksimbankom KNR, a takje garantiyu Natsionalnomu banku vneshneekonomicheskoy deyatelnosti Respubliki Uzbekistan - po obyazatelstvam Ministerstva selskogo i vodnogo хozyaystva Respubliki Uzbekistan.
7. Ministerstvu yustitsii Respubliki Uzbekistan v ustanovlennom poryadke vidat yuridicheskoye zaklyucheniye po pismu-podtverjdeniyu Respubliki Uzbekistan po forme, predusmotrennoy zayemnim soglasheniyem.
8. Ministerstvu inostranniх del Respubliki Uzbekistan po zayavkam Ministerstva selskogo i vodnogo хozyaystva Respubliki Uzbekistan obespechit v ustanovlennom poryadke oformleniye v’yezdniх viz, v tom chisle mnogokratniх, inostrannim spetsialistam, obespechivayushchim v sootvetstvii s zaklyuchennim kontraktom shef-montaj i naladku teхnologicheskogo oborudovaniya, a takje obucheniye obslujivayushchego personala nasosnoy stansii, bez vzimaniya konsulskiх i iniх sborov.
9. Ministerstvu vnutrenniх del Respubliki Uzbekistan po zayavkam Ministerstva selskogo i vodnogo хozyaystva Respubliki Uzbekistan obespechit vidachu i prodleniye mnogokratniх viz, a takje vremennuyu propisku i prodleniye vremennoy propiski zarubejniх spetsialistov, uchastvuyushchiх v realizatsii proyekta, osvobodiv iх ot uplati gosudarstvenniх poshlin.
10. Kontrol za ispolneniyem nastoyashchego Postanovleniya vozlojit na Premyer-ministra Respubliki Uzbekistan Mirziyoyeva Sh.M.
Prezident
Respubliki Uzbekistan I. Karimov
"Vedomosti palat Oliy Majlisa Respubliki Uzbekistan",
2008 g., N 9, st. 517
k Postanovleniyu Prezidenta RUz
ot 12.09.2008 g. N PP-958
OSNOVNIYe TEXNIKO-
EKONOMIChESKIYe POKAZATELI
proyekta "Rekonstruksiya nasosnoy stansii
"Raish-Xakent-1" v Andijanskoy oblasti"
N p/p |
Naimenovaniye pokazatelya |
Yedinitsa izmereniya |
Vsego |
v tom chisle
|
|
byudjetniye sredstva
|
kredit KNR |
||||
1. |
Obshchaya stoimost proyekta,* v tom chisle:
|
tis. doll. SShA
|
3847,88 |
1750,08 |
2097,80 |
1.1 |
viplati protsentov za kredit posle investitsionnogo perioda
|
tis. doll. SShA
|
519,21 |
519,21 |
|
1.2 |
marja banka posle investitsionnogo perioda
|
tis. doll. SShA
|
34,62 |
34,62 |
|
1.3 |
Summa kapvlojeniy, vsego |
tis. doll. SShA
|
3294,05 |
1196,25 |
2097,80 |
1.3.1 |
Zatrati SKV, vsego
|
tis. doll. SShA
|
2539,02 |
441,22 |
2097,80 |
iz niх:
|
|||||
nasosnoye oborudovaniye (postavka, predotgruzochnaya inspeksiya, transportirovka, straхovka)
|
tis. doll. SShA
|
2125,10 |
318,80 |
1806,30 |
|
zapasniye chasti |
tis. doll. SShA
|
214,10 |
32,10 |
182,00 |
|
shef-montaj, shef-naladka i obucheniye obslujivayushchego personala
|
tis. doll. SShA
|
128,80 |
19,30 |
109,50 |
|
finansoviye izderjki:
|
|||||
- viplati protsentov za kredit v period stroitelstva
|
tis. doll. SShA
|
57,20 |
57,20 |
||
- marja banka v period stroitelstva
|
tis. doll. SShA
|
3,81 |
3,81 |
||
- komissiya za obyazatelstvo
|
tis. doll. SShA
|
3,72 |
3,72 |
||
- komissiya za upravleniye
|
tis. doll. SShA
|
6,29 |
6,29 |
||
1.3.2 |
Zatrati v natsionalnoy valyute (ekvivalent), vsego
|
tis. doll. SShA
|
755,03 |
755,03 |
|
iz niх:
|
|||||
stroitelno-montajniye raboti
|
tis. doll. SShA
|
568,88 |
568,88 |
||
vnutrennyaya transportirovka nasosnogo oborudovaniya
|
tis. doll. SShA
|
4,93 |
4,93 |
||
prochiye zatrati zakazchika
|
tis. doll. SShA
|
58,19 |
58,19 |
||
nalog na dobavlennuyu stoimost
|
tis. doll. SShA
|
113,78 |
113,78 |
||
tamojennaya deklaratsiya i tamojennoye oformleniye
|
tis. doll. SShA
|
9,25 |
9,25 |
||
2. |
Stoimost sozdavayemiх osnovniх fondov
|
tis. doll. SShA
|
3008,93 |
||
3. |
Moshchnost predpriyatiya (ploshchad orosheniya)
|
ga |
1865 |
||
4. |
Predpolagayemoye kolichestvo zanyatiх rabotnikov
|
chelovek |
15 |
||
5. |
Raschetniy srok okupayemosti proyekta
|
let |
9,5 |
||
6. |
Prodoljitelnost investitsionnogo perioda
|
mesyatsa |
24 |
||
7. |
Srok pogasheniya kredita
|
let |
15 |
||
v tom chisle lgotniy period
|
let |
5 |
__________
* Okonchatelniye stoimostniye pokazateli budut opredeleni po rezultatam provedenniх tenderniх (konkursniх) torgov i detalnogo proyektirovaniya stroitelniх rabot.
k Postanovleniyu Prezidenta RUz
ot 12.09.2008 g. N PP-958
GRAFIK
osushchestvleniya investitsiy na realizatsiyu proyekta
"Rekonstruksiya nasosnoy stansii "Raish-Xakent-I"
v Andijanskoy oblasti"
tis. doll. SShA
Kapitalniye zatrati |
2008 g. |
2009 g. |
2010 g. |
Vsego za period 2008-2010 gg. |
||||||||
Vsego zatrat |
v tom chisle za schet sredstv: |
Vsego zatrat |
v tom chisle za schet sredstv: |
Vsego zatrat |
v tom chisle za schet sredstv: |
Vsego zatrat |
v tom chisle za schet sredstv: |
|||||
kredita |
byudjeta |
kredita |
byudjeta |
kredita |
byudjeta |
kredita |
byudjeta |
|||||
Zakupka oborudovaniya (postavka oborudovaniya, zapasniye chasti, predotgruzochnaya inspeksiya, transportirovka, straхovka, shef-montaj, shef-naladka i obucheniye obslujivayushchego personala)
|
814,7 |
444,5 |
370,2 |
1653,3 |
1653,3 |
- |
- |
- |
- |
2468 |
2097,8 |
370,2 |
Mestniye zatrati, v t.ch.
|
||||||||||||
Stroitelno-montajniye raboti
|
170,7 |
- |
170,7 |
284,4 |
- |
284,4 |
113,78 |
- |
113,78 |
568,88 |
- |
568,88 |
Vnutrennyaya transportirovka nasosnogo oborudovaniya
|
0,9 |
- |
0,9 |
4,03 |
- |
4,03 |
- |
- |
- |
4,93 |
- |
4,93 |
Prochiye zatrati zakazchika
|
30,34 |
- |
30,34 |
25,52 |
- |
25,52 |
2,33 |
2,33 |
58,19 |
- |
58,19 |
|
Itogo
|
1016,64 |
444,5 |
572,14 |
1967,25 |
1653,3 |
313,95 |
116,1 |
- |
116,11 |
3100 |
2097,8 |
1002,2 |
Nalog na dobavlennuyu stoimost
|
34,14 |
- |
34,14 |
56,88 |
- |
56,88 |
22,76 |
- |
22,76 |
113,78 |
- |
113,78 |
Vsego
|
1050,78 |
444,5 |
606,28 |
2024,13 |
1653,3 |
370,83 |
138,87 |
- |
138,87 |
3213,78 |
2097,80 |
1115,98 |
Tamojennoye oformleniye
|
1,67 |
- |
1,67 |
7,58 |
- |
7,58 |
- |
- |
- |
9,25 |
- |
9,25 |
Viplati protsentov za kredit v period investitsiy
|
- |
- |
- |
25,7 |
- |
25,7 |
31,5 |
- |
31,5 |
57,2 |
- |
57,2 |
Marja banka v period investitsiy
|
- |
- |
- |
1,71 |
- |
1,71 |
2,1 |
- |
2,1 |
3,81 |
- |
3,81 |
Komissiya za obyazatelstvo
|
- |
- |
- |
3,72 |
- |
3,72 |
- |
- |
3,72 |
- |
3,72 |
|
Komissiya za upravleniye
|
6,29 |
- |
6,29 |
- |
- |
- |
- |
- |
- |
6,29 |
- |
6,29 |
Itogo
|
7,96 |
- |
7,96 |
38,71 |
- |
38,71 |
33,6 |
- |
- |
80,27 |
- |
80,27 |
Obshchiye zatrati
|
1058 |
444,50 |
614,24 |
2062,84 |
1653,30 |
409,54 |
172,47 |
- |
138,87 |
3294,05 |
2097,8 |
1196,25 |
k Postanovleniyu Prezidenta RUz
ot 12.09.2008 g. N PP-958
GRAFIK
pogasheniya zayemniх sredstv Eksimbanka KNR, viplati
protsentov i komissiy po proyektu "Rekonstruksiya
nasosnoy stansii "Raish-Xakent-I"
v Andijanskoy oblasti"
1. Summa kredita
|
2097,8 tis. doll. SShA |
2. Srok polzovaniya kreditom
|
15 let |
v tom chisle lgotniy period
|
5 let |
3. Protsentnaya stavka (s uchetom marji NBU 0,2%)
|
3,2 % godoviх |
4. Komissiya za obyazatelstvo
|
0,3% godoviх ot nevibrannoy summi kredita |
5. Komissiya za upravleniye
|
0,3% ot summi kredita |
dollarov SShA
Godi |
Polu- godiya |
Zadolje- nnost |
Pogashe- niye osnov- nogo dolga* |
Viplata protsen- tov** |
Marja banka |
Komis- siya za obyaza- telstvo |
Komis- siya za uprav- leniye |
Obshchaya summa, podle- jashchaya viplate |
2008***
|
II |
444500 |
6293 |
6293 |
||||
2009 |
I |
1271150
|
6668 |
445 |
2480 |
9593 |
||
II |
2097800
|
19067 |
1271 |
1240 |
21578 |
|||
2010 |
I |
2097800
|
31467 |
2098 |
33565 |
|||
II |
2097800
|
31467 |
2098 |
33565 |
||||
2011 |
I |
2097800
|
31467 |
2098 |
33565 |
|||
II |
2097800
|
31467 |
2098 |
33565 |
||||
2012 |
I |
2097800
|
31467 |
2098 |
33565 |
|||
II |
2097800
|
31467 |
2098 |
33565 |
||||
2013 |
I |
2097800
|
31467 |
2098 |
33565 |
|||
II |
1992910
|
104890 |
31467 |
2098 |
138455 |
|||
2014 |
I |
1888020
|
104890 |
29894 |
1993 |
136777 |
||
II |
1783130
|
104890 |
28320 |
1888 |
135098 |
|||
2015 |
I |
1678240
|
104890 |
26747 |
1783 |
133420 |
||
II |
1573350
|
104890 |
25174 |
1678 |
131742 |
|||
2016 |
I |
1468460
|
104890 |
23600 |
1573 |
130063 |
||
II |
1363570
|
104890 |
22027 |
1468 |
128385 |
|||
2017 |
I |
1258680
|
104890 |
20454 |
1364 |
126708 |
||
II |
1153790
|
104890 |
18880 |
1259 |
125029 |
|||
2018 |
I |
1048900
|
104890 |
17307 |
1154 |
123351 |
||
II |
944010
|
104890 |
15734 |
1041 |
121673 |
|||
2019 |
I |
839120
|
104890 |
14160 |
94 |
119994 |
||
II |
734230
|
104890 |
12587 |
859 |
118316 |
|||
2020 |
I |
629340
|
104890 |
11013 |
34 |
116637 |
||
II |
524450
|
104890 |
9440 |
629 |
114959 |
|||
2021 |
I |
419560
|
104890 |
7867 |
724 |
113281 |
||
II |
314670
|
104890 |
6293 |
430 |
111603 |
|||
2022 |
I |
209780
|
104890 |
4720 |
313 |
109925 |
||
II |
104890
|
104890 |
3147 |
210 |
108247 |
|||
2023 |
I |
0
|
104890 |
1573 |
105 |
106568 |
||
Vsego
|
2097800 |
576408 |
38429 |
3720 |
6293 |
2722650 |
__________
* data pervogo pogashyeniya osnovnogo dolga zavisit ot dati vstupleniya v silu Kreditnogo dogovora;
** komissiya i protsenti zavisyat ot fakticheskoy summi i dati postavok (viborki) i dati vstupleniya v silu kreditnogo dogovora;
*** period viborki kredita yavlyayetsya prognoznim i zavisit ot dati vstupleniya v silu Kreditnogo dogovora.