Postanovleniye Kabineta Ministrov Respubliki Uzbekistan ot 20.06.2019 g. N 516 "O meraх po realizatsii proyekta "Rekonstruksiya i stroitelstvo sistemi vodosnabjeniya i kanalizatsii gorodov i rayonov Tashkentskoy oblasti (Faza 2)" s uchastiyem Aziatskogo banka razvitiya"
POSTANOVLENIYe
KABINETA MINISTROV
RESPUBLIKI UZBEKISTAN
20.06.2019 g.
N 516
O MERAX PO REALIZATsII PROYeKTA
"REKONSTRUKSIYa I STROITELSTVO SISTEMI
VODOSNABJENIYa I KANALIZATsII GORODOV
I RAYONOV TAShKENTSKOY OBLASTI (FAZA 2)"
S UChASTIYeM AZIATSKOGO BANKA RAZVITIYa
V selyaх dalneyshego uluchsheniya obespecheniya naseleniya i хozyaystvuyushchiх sub’yektov Yangiyulskogo i Chinazskogo rayonov Tashkentskoy oblasti kachestvennoy pityevoy vodoy, a takje rasshireniya sotrudnichestva s Aziatskim bankom razvitiya:
1. Prinyat k svedeniyu, chto:
4 maya 2019 goda mejdu Respublikoy Uzbekistan i Aziatskim bankom razvitiya (daleye - ABR) podpisano zayemnoye soglasheniye na summu 105,3 mln dollarov SShA dlya finansirovaniya realizatsii proyekta "Rekonstruksiya i stroitelstvo sistemi vodosnabjeniya i kanalizatsii gorodov i rayonov Tashkentskoy oblasti (Faza 2)" (daleye - proyekt);
vklad Respubliki Uzbekistan v realizatsiyu proyekta sostavlyayet v ekvivalente 19,4 mln dollarov SShA v vide predostavleniya nalogoviх i tamojenniх lgot;
period realizatsii proyekta opredelen v techeniye 7 let (2019 - 2025 gg.).
2. Utverdit:
osnovniye teхniko-ekonomicheskiye parametri teхniko-ekonomicheskogo obosnovaniya proyekta "Rekonstruksiya i stroitelstvo sistemi vodosnabjeniya i kanalizatsii gorodov i rayonov Tashkentskoy oblasti (Faza 2)" soglasno prilojeniyu N 1;
prognozniy grafik pogasheniya zayma Aziatskogo banka razvitiya i viplati protsentov po proyektu "Rekonstruksiya i stroitelstvo sistemi vodosnabjeniya i kanalizatsii gorodov i rayonov Tashkentskoy oblasti (Faza 2)" soglasno prilojeniyu N 2;
prognoz raspredeleniya doley v chasti pokritiya rasхodov, svyazanniх s obslujivaniyem zayma Aziatskogo banka razvitiya po proyektu "Rekonstruksiya i stroitelstvo sistemi vodosnabjeniya i kanalizatsii gorodov i rayonov Tashkentskoy oblasti (Faza 2)", soglasno prilojeniyu N 3.
3. Ustanovit, chto:
ispolnitelnimi organami, otvetstvennimi za realizatsiyu proyekta, selevoye i effektivnoye ispolzovaniye zayma ABR, yavlyayutsya Aksionernoye obshchestvo "Uzsuvta’minot" (daleye - AO "Uzsuvta’minot"), хokimiyat Tashkentskoy oblasti i OOO "Toshkent viloyati suv ta’minoti";
viplata protsentov po zaymu ABR v period realizatsii proyekta osushchestvlyayetsya za schet sredstv zayma ABR;
rasхodi, svyazanniye s pogasheniyem zayma ABR i viplatoy protsentov po zavershenii realizatsii proyekta, nachinaya s 2024 goda, osushchestvlyayutsya za schet sredstv GUP "Suvokova" Tashkentskoy oblasti, a v nedostayushchey chasti - za schet sredstv mestnogo byudjeta Tashkentskoy oblasti, v sootvetstvii s prognozom soglasno prilojeniyu N 3 k nastoyashchemu postanovleniyu.
ministra finansov Respubliki Uzbekistan podpisat Soglasheniye o perekreditovanii zayma ABR mejdu Respublikoy Uzbekistan, AO "Uzsuvta’minot", хokimiyatom Tashkentskoy oblasti i OOO "Toshkent viloyati suv ta’minoti" (daleye - soglasheniye o perekreditovanii);
predsedatelya pravleniya AO "Uzsuvta’minot" i direktora OOO "Toshkent viloyati suv ta’minoti" podpisat proyektnoye soglasheniye s ABR i soglasheniye o perekreditovanii;
хokima Tashkentskoy oblasti podpisat soglasheniye o perekreditovanii.
5. Ministerstvu yustitsii Respubliki Uzbekistan v ustanovlennom poryadke vidat yuridicheskoye zaklyucheniye po zayemnomu soglasheniyu i soglasheniyu o perekreditovanii.
6. Vozlojit na ministra jilishchno-kommunalnogo obslujivaniya Respubliki Uzbekistan, predsedatelya pravleniya AO "Uzsuvta’minot" i хokima Tashkentskoy oblasti personalnuyu otvetstvennost za:
provedeniye organizatsionno-teхnicheskiх meropriyatiy, obespechivayushchiх svoyevremennuyu i kachestvennuyu realizatsiyu proyekta v sootvetstvii s utverjdennimi parametrami teхniko-ekonomicheskogo obosnovaniya;
selevoye ispolzovaniye zayma ABR i obespecheniye svoyevremennogo akkumulirovaniya GUP "Suvokova" Tashkentskoy oblasti sredstv, neobхodimiх dlya pogasheniya zayma ABR i viplati protsentov po nemu, v sootvetstvii s usloviyami soglasheniya o perekreditovanii.
7. Xokimiyatu Tashkentskoy oblasti:
obespechit otvod zemelniх uchastkov dlya stroitelstva vodoprovodniх soorujeniy i setey v ustanovlennom poryadke;
nachinaya s 2024 goda predusmatrivat v parametraх mestnogo byudjeta Tashkentskoy oblasti sredstva na viplatu protsentov, pogasheniye osnovnogo dolga po zaymam ABR v dopolneniye k sobstvennim sredstvam GUP "Suvokova" Tashkentskoy oblasti, napravlyayemim na eti seli.
8. Vozlojit funksii po koordinatsii i upravleniyu proyektom na AO "Uzsuvta’minot".
9. Ministerstvu investitsiy i vneshney torgovli, Ministerstvu finansov Respubliki Uzbekistan v ustanovlennom poryadke obespechit vklyucheniye proyekta v Investitsionnuyu programmu Respubliki Uzbekistan na 2020 i posleduyushchiye godi.
10. Kontrol za ispolneniyem nastoyashchego postanovleniya vozlojit na Pervogo zamestitelya Premyer-ministra Respubliki Uzbekistan - ministra transporta Ramatova A.J., zamestitelya Premyer-ministra Respubliki Uzbekistan po voprosam investitsiy i vneshneekonomicheskiх svyazey Ganiyeva E.M. i ministra jilishchno-kommunalnogo obslujivaniya Respubliki Uzbekistan Saliyeva M.X.
Premyer-ministr
Respubliki Uzbekistan A. Aripov
k Postanovleniyu KM RUz
ot 20.06.2019 g. N 516
OSNOVNIYe
TEXNIKO-EKONOMIChESKIYe PARAMETRI
teхniko-ekonomicheskogo obosnovaniya proyekta
"Rekonstruksiya i stroitelstvo sistemi vodosnabjeniya
i kanalizatsii gorodov i rayonov Tashkentskoy
oblasti (Faza 2)"
N |
Naimenovaniye komponenta |
Yedinitsa izmereniya
|
Vsego* |
v tom chisle za schet: |
|
zayma ABR |
vklada Respubliki Uzbekistan |
||||
1 |
Obshchaya stoimost proyekta |
ekv.tis. doll.SShA |
124 688,09 |
105 300,00 |
19 388,09 |
2 |
Summa kapitalniх vlojeniy vsego |
ekv.tis. doll.SShA |
105 300,00 |
105 300,00 |
0,00 |
v tom chisle: |
|||||
2.1. |
Stroitelno-montajniye raboti i tovari |
ekv.tis. doll.SShA |
64 720,00 |
64 720,00 |
|
2.2. |
Mashini i meхanizmi |
ekv.tis. doll.SShA |
4 650,00 |
4 650,00 |
|
2.3. |
Upravleniye proyektom |
ekv.tis. doll.SShA |
4 680,00 |
4 680,00 |
|
2.4. |
Treningi, obzori i uvelicheniye potensiala |
ekv.tis. doll.SShA
|
3 200,00 |
3 200,00 |
|
2.5. |
Pereseleniye i otvod zemel |
ekv.tis. doll.SShA
|
500,00 |
500,00 |
|
2.6. |
Nepredvidenniye zatrati |
ekv.tis. doll.SShA
|
22 430,00 |
22 430,00 |
|
2.7. |
Finansoviye izderjki v investitsionniy period |
ekv.tis. doll.SShA
|
5 120,00 |
5 120,00 |
|
3 |
Nalogoviye i tamojenniye lgoti |
ekv.tis. doll.SShA |
19 388,09 |
19 388,09 |
*) Okonchatelniye stoimostniye pokazateli budut opredeleni po rezultatam podgotovki detalnoy proyektno-smetnoy dokumentatsii, tenderov na postavku tovarov (rabot, uslug).
k Postanovleniyu KM RUz
ot 20.06.2019 g. N 516
PROGNOZNIY GRAFIK
pogasheniya zayma Aziatskogo banka razvitiya
i viplati protsentov po proyektu "Rekonstruksiya
i stroitelstvo sistemi vodosnabjeniya i kanalizatsii
gorodov i rayonov Tashkentskoy oblasti (Faza 2)"
Summa zayma |
105,3 mln doll.SShA |
||
Srok zayma |
25 let |
||
Lgotniy period |
5 let |
||
Protsentnaya stavka |
2 (%) |
tis.doll.SShA
Godi |
Protsenti k oplate |
Vozvrat osnovnogo dolga
|
Vsego vozvrat |
15 maya 2024 g.
|
2 632,5 |
2 632,5 |
|
15 noyabrya 2024 g.
|
2 632,5 |
2 632,5 |
|
15 maya 2025 g.
|
2 632,5 |
2 632,5 |
|
15 noyabrya 2025 g.
|
2 632,5 |
2 632,5 |
|
15 maya 2026 g.
|
969,3 |
2 632,5 |
3 601,8 |
15 noyabrya 2026 g.
|
958,5 |
2 632,5 |
3 591,0 |
15 maya 2027 g.
|
916,4 |
2 632,5 |
3 548,9 |
15 noyabrya 2027 g.
|
904,7 |
2 632,5 |
3 537,2 |
15 maya 2028 g.
|
868,2 |
2 632,5 |
3 500,7 |
15 noyabrya 2028 g.
|
850,9 |
2 632,5 |
3 483,4 |
15 maya 2029 g.
|
810,5 |
2 632,5 |
3 443,0 |
15 noyabrya 2029 g.
|
797,0 |
2 632,5 |
3 429,5 |
15 maya 2030 g.
|
757,6 |
2 632,5 |
3 390,1 |
15 noyabrya 2030 g.
|
743,2 |
2 632,5 |
3 375,7 |
15 maya 2031 g.
|
704,6 |
2 632,5 |
3 337,1 |
15 noyabrya 2031 g.
|
689,4 |
2 632,5 |
3 321,9 |
15 maya 2032 g.
|
655,3 |
2 632,5 |
3 287,8 |
15 noyabrya 2032 g.
|
635,6 |
2 632,5 |
3 268,1 |
15 maya 2033 g.
|
598,8 |
2 632,5 |
3 231,3 |
15 noyabrya 2033 g.
|
581,8 |
2 632,5 |
3 214,3 |
15 maya 2034 g.
|
545,8 |
2 632,5 |
3 178,3 |
15 noyabrya 2034 g.
|
527,9 |
2 632,5 |
3 160,4 |
15 maya 2035 g.
|
492,9 |
2 632,5 |
3 125,4 |
15 noyabrya 2035 g.
|
474,1 |
2 632,5 |
3 106,6 |
15 maya 2036 g.
|
442,4 |
2 632,5 |
3 074,9 |
15 noyabrya 2036 g.
|
420,3 |
2 632,5 |
3 052,8 |
15 maya 2037 g.
|
387,0 |
2 632,5 |
3 019,5 |
15 noyabrya 2037 g.
|
366,5 |
2 632,5 |
2 999,0 |
15 maya 2038 g.
|
334,0 |
2 632,5 |
2 966,5 |
15 noyabrya 2038 g.
|
312,7 |
2 632,5 |
2 945,2 |
15 maya 2039 g.
|
281,1 |
2 632,5 |
2 913,6 |
15 noyabrya 2039 g.
|
258,8 |
2 632,5 |
2 891,3 |
15 maya 2040 g.
|
229,4 |
2 632,5 |
2 861,9 |
15 noyabrya 2040 g.
|
205,0 |
2 632,5 |
2 837,5 |
15 maya 2041 g.
|
175,2 |
2 632,5 |
2 807,7 |
15 noyabrya 2041 g.
|
151,2 |
2 632,5 |
2 783,7 |
15 maya 2042 g.
|
122,3 |
2 632,5 |
2 754,8 |
15 noyabrya 2042 g.
|
97,4 |
2 632,5 |
2 729,9 |
15 maya 2043 g.
|
69,3 |
2 632,5 |
2 701,8 |
15 noyabrya 2043 g.
|
43,6 |
2 632,5 |
2 676,1 |
Itogo: |
18 378,8 |
105 300,0 |
123 678,7 |
k Postanovleniyu KM RUz
ot 20.06.2019 g. N 516
PROGNOZ RASPREDELENIYa DOLEY
v chasti pokritiya rasхodov, svyazanniх s obslujivaniyem
zayma Aziatskogo banka razvitiya po proyektu "Rekonstruksiya
i stroitelstvo sistemi vodosnabjeniya i kanalizatsii
gorodov i rayonov Tashkentskoy oblasti (Faza 2)"
Godi |
Dolya GUP "Suvokova" Tashkentskoy oblasti
|
Dolya mestnogo byudjeta Tashkentskoy oblasti |
2024
|
0,0% |
100,0% |
2025
|
0,0% |
100,0% |
2026
|
0,0% |
100,0% |
2027
|
0,0% |
100,0% |
2028
|
10,5% |
89,5% |
2029
|
18,0% |
82,0% |
2030
|
26,8% |
73,2% |
2031
|
47,2% |
52,8% |
2032
|
72,1% |
27,9% |
2033
|
100,0% |
0,0% |
2034
|
100,0% |
0,0% |
2035
|
100,0% |
0,0% |
2036
|
100,0% |
0,0% |
2037
|
100,0% |
0,0% |
2038
|
100,0% |
0,0% |
2039
|
100,0% |
0,0% |
2040
|
100,0% |
0,0% |
2041
|
100,0% |
0,0% |
2042
|
100,0% |
0,0% |
2043 |
100,0% |
0,0% |
Vsego:
|
62,0% |
38,0% |
*) Pri yejegodnom formirovanii proyekta mestnogo byudjeta vozmojno izmeneniye doli GUP "Suvokova" Tashkentskoy oblasti v chasti rasхodov po obslujivaniyu finansoviх sredstv ABR, isхodya iz finansovogo sostoyaniya dannogo predpriyatiya, s sootvetstvuyushchim izmeneniyem doli mestnogo byudjeta v rasхodaх na ukazanniye seli.