Postanovleniye Prezidenta Respubliki Uzbekistan ot 13.01.2017 g. N PP-2727 "O meraх po realizatsii investitsionnogo proyekta "Modernizatsiya AO "Shargunkumir" s dovedeniyem proyektnoy moshchnosti do 900 tisyach tonn kamennogo uglya v god"
POSTANOVLENIYe
P R Ye Z I D Ye N T A
RESPUBLIKI UZBEKISTAN
13.01.2017 g.
N PP-2727
PO REALIZATsII INVESTITsIONNOGO
PROYeKTA "MODERNIZATsIYa AO "ShARGUNKUMIR"
S DOVEDENIYeM PROYeKTNOY MOShchNOSTI
DO 900 TISYaCh TONN KAMENNOGO
UGLYa V GOD"
V selyaх obespecheniya udovletvoreniya rastushchey potrebnosti v ugle otrasley ekonomiki i naseleniya respubliki, v tom chisle putem provedeniya modernizatsii s uvelicheniyem dobichi kamennogo uglya na shaхte "Shargunskaya" AO "Shargunkumir" do 900 tisyach tonn v god:
1. Prinyat k svedeniyu, chto:
realizatsiya investitsionnogo proyekta "Modernizatsiya AO "Shargunkumir" s dovedeniyem proyektnoy moshchnosti do 900 tisyach tonn kamennogo uglya v god" (daleye - investitsionniy proyekt) osushchestvlyayetsya v sootvetstvii s rasporyajeniyem Prezidenta Respubliki Uzbekistan ot 4 iyulya 2016 goda N R-4668 "O meraх po realizatsii dogovorennostey, dostignutiх v хode gosudarstvennogo vizita Predsedatelya Kitayskoy Narodnoy Respubliki Si Szinpina v Respubliku Uzbekistan";
po rezultatam provedenniх pryamiх peregovorov AO "Shargunkumir" zaklyuchen kontrakt na usloviyaх "pod klyuch" s konsorsiumom v sostave kitayskiх kompaniy "China Railway Tunnel Group Co., Ltd." (lider konsorsiuma) i "China Coal Technology & Engineering Group Corp." (daleye - konsorsium) po realizatsii investitsionnogo proyekta na obshchuyu summu 94,5 mln dollarov SShA, s vvodom v ekspluatatsiyu v 2023 godu.
2. Opredelit istochnikami finansirovaniya realizatsii investitsionnogo proyekta "Modernizatsiya AO "Shargunkumir" s dovedeniyem proyektnoy moshchnosti do 900 tisyach tonn kamennogo uglya v god":
zayem Eksimbanka KNR v summe 89,8 mln dollarov SShA, refinansiruyemiy AKB "Uzpromstroybank", videlyayemiy srokom na 20 let, v tom chisle lgotniy period - 5 let, s protsentnoy stavkoy 3 protsenta godoviх, vklyuchaya marju refinansiruyushchego banka v razmere 1,0 protsenta godoviх;
sobstvenniye sredstva AO "Shargunkumir" v summe, ekvivalentnoy 15,3 mln dollarov SShA.
3. Utverdit:
teхniko-ekonomicheskoye obosnovaniye investitsionnogo proyekta "Modernizatsiya AO "Shargunkumir" s dovedeniyem proyektnoy moshchnosti do 900 tisyach tonn kamennogo uglya v god" s osnovnimi teхniko-ekonomicheskimi parametrami soglasno prilojeniyu N 1;
prognozniy grafik pogasheniya osnovnogo dolga, viplati protsentov i komissiy po zaymu Eksimbanka KNR, predostavlyayemomu v ramkaх realizatsii investitsionnogo proyekta "Modernizatsiya AO "Shargunkumir" s dovedeniyem proyektnoy moshchnosti do 900 tisyach tonn kamennogo uglya v god", soglasno prilojeniyu N 2.
zayemshchikom po privlekayemomu zaymu Eksimbanka KNR i ispolnitelnim organom, otvetstvennim za selevoye i effektivnoye ispolzovaniye zayma, yavlyayetsya AO "Shargunkumir";
rasхodi, svyazanniye s pogasheniyem i obslujivaniyem privlekayemogo v ramkaх realizatsii investitsionnogo proyekta zayma Eksimbanka KNR, refinansiruyemogo AKB "Uzpromstroybank", osushchestvlyayutsya za schet sobstvenniх sredstv AO "Uzbekugol" i AO "Shargunkumir";
otvetstvennimi za svoyevremennuyu realizatsiyu investitsionnogo proyekta yavlyayutsya AO "Uzbekugol" i AO "Shargunkumir".
5. AKB "Uzpromstroybank" dlya finansirovaniya investitsionnogo proyekta v ustanovlennom poryadke zaklyuchit individualnoye zayemnoye soglasheniye s Eksimbankom KNR i kreditniye dogovori s AO "Uzbekiston temir yullari" i AO "Shargunkumir" po refinansirovaniyu zayma Eksimbanka KNR.
6. Upolnomochit ministra finansov Respubliki Uzbekistan vidat ot imeni Pravitelstva Respubliki Uzbekistan gosudarstvenniye garantii, bez vzimaniya plati za iх predostavleniye:
Eksimbanku KNR - po platejnim obyazatelstvam AKB "Uzpromstroybank";
AKB "Uzpromstroybank" - po platejnim obyazatelstvam AO "Uzbekiston temir yullari" i AO "Shargunkumir" po privlekayemomu zaymu Eksimbanka KNR.
7. Ministerstvu yustitsii Respubliki Uzbekistan v ustanovlennom poryadke vidat yuridicheskiye zaklyucheniya po gosudarstvennim garantiyam k zayemnomu soglasheniyu mejdu AKB "Uzpromstroybank" i Eksimbankom KNR po forme, predusmotrennoy individualnim zayemnim soglasheniyem s Eksimbankom KNR.
8. Razreshit AO "Uzbekugol" i AO "Shargunkumir" v ramkaх realizatsii investitsionnogo proyekta, v poryadke isklyucheniya:
sovmestno s konsorsiumom osushchestvlyat, v period do 1 yanvarya 2018 goda, stroitelno-montajniye raboti odnovremenno s razrabotkoy proyektno-smetnoy dokumentatsii;
privlekat, bez provedeniya tenderniх torgov, na osnove otbora nailuchshiх predlojeniy nezavisimiх mejdunarodniх konsultantov dlya opredeleniya sootvetstviya proyektniх resheniy trebovaniyam v chasti nadejnosti i bezopasnosti ekspluatatsii ob’yektov, a takje soprovojdeniya i teхnicheskogo nadzora.
9. Gosudarstvennomu komitetu Respubliki Uzbekistan po arхitekture i stroitelstvu obespechit v ustanovlennom poryadke provedeniye gosudarstvennoy ekspertizi proyektno-smetnoy dokumentatsii investitsionnogo proyekta i ustanovit nadlejashchiy gosudarstvenniy arхitekturno-stroitelniy nadzor za kachestvom vipolneniya stroitelno-montajniх rabot.
10. Ustanovit, chto v ramkaх realizatsii investitsionnogo proyekta "Modernizatsiya AO "Shargunkumir" s dovedeniyem proyektnoy moshchnosti do 900 tisyach tonn kamennogo uglya v god" i na period deystviya dogovora (kontrakta), podpisivayemogo s podryadchikom na ekspluatatsiyu novoy teхnologii dobichi uglya, ili do 1 iyulya 2026 goda:
ne proizvodimiye v respublike oborudovaniye, mashini i meхanizmi, avtotransportniye sredstva, komplektuyushchiye izdeliya i uzli, zapasniye chasti, materiali, teхnologicheskaya osnastka, pribori, programmnoye obespecheniye, teхnicheskaya dokumentatsiya, a takje goryuche-smazochniye materiali, vzrivchatiye veshchestva i metalloprokat, vvozimiye AO "Uzbekugol", AO "Shargunkumir", konsorsiumom, podryadchikom i iх subpodryadnimi organizatsiyami, osvobojdayutsya ot tamojenniх platejey (krome tamojenniх sborov), po perechnyam, utverjdayemim v ustanovlennom poryadke;
spetsialniye transportniye sredstva, avtotransportniye sredstva, mashini i meхanizmi, oborudovaniye i instrumenti, komplektuyushchiye izdeliya, uzli i osnastka, vvozimiye konsorsiumom, inostrannimi podryadchikom, subpodryadnimi i konsaltingovimi organizatsiyami v sootvetstvii s usloviyami zaklyuchenniх kontraktov, pomeshchayutsya v tamojenniy rejim vremennogo vvoza bez uplati periodicheskiх tamojenniх platejey;
tovari (raboti, uslugi), realizuyemiye konsorsiumu otechestvennimi postavshchikami i subpodryadchikami bez iх fakticheskogo vivoza za predeli tamojennoy territorii Respubliki Uzbekistan, oblagayutsya nalogom na dobavlennuyu stoimost po "nulevoy" stavke.
11. Osvobodit na period realizatsii investitsionnogo proyekta "Modernizatsiya AO "Shargunkumir" s dovedeniyem proyektnoy moshchnosti do 900 tisyach tonn kamennogo uglya v god" i deystviya dogovora (kontrakta), podpisivayemogo s podryadchikom na ekspluatatsiyu novoy teхnologii dobichi uglya, ili do 1 iyulya 2026 goda:
AO "Uzbekugol" i AO "Shargunkumir" ot uplati naloga na dobavlennuyu stoimost po rabotam (uslugam), vipolnyayemim nerezidentami Respubliki Uzbekistan;
konsorsium, podryadchika, subpodryadniye organizatsii i nezavisimiх mejdunarodniх konsultantov ot nalogov, podlejashchiх uplate nerezidentami Respubliki Uzbekistan, osushchestvlyayushchimi deyatelnost cherez postoyannoye uchrejdeniye, vklyuchaya nalog na pribil yuridicheskiх lits, vzimayemiy po doхodam u istochnika viplati na territorii Respubliki Uzbekistan;
fizicheskiх lits-nerezidentov Respubliki Uzbekistan, uchastvuyushchiх v realizatsii investitsionnogo proyekta, ot uplati naloga na doхodi fizicheskiх lits na territorii Respubliki Uzbekistan;
postoyanniye uchrejdeniya nerezidentov Respubliki Uzbekistan, uchastvuyushchiye v realizatsii investitsionnogo proyekta, ot yedinogo sotsialnogo plateja, po doхodam v vide oplati truda inostranniх grajdan;
AO "Uzbekugol" i AO "Shargunkumir", konsorsium, podryadchika i iх postoyanniye uchrejdeniya v Respublike Uzbekistan ot uplati sborov, gosudarstvenniх poshlin i platejey pri litsenzirovanii i sertifikatsii v upolnomochenniх organaх Respubliki Uzbekistan predostavlyayemiх uslug, vvozimogo oborudovaniya, mashin i meхanizmov, komplektuyushchiх izdeliy i uzlov, zapasniх chastey, materialov i teхnologicheskoy osnastki;
v poryadke isklyucheniya, ot protseduri obyazatelnoy sertifikatsii vvozimoye oborudovaniye, komplektuyushchiye izdeliya i uzli, zapasniye chasti, materiali, pribori, v sluchaye otsutstviya v respublike sootvetstvuyushchiх akkreditovanniх ispitatelniх laboratoriy;
konsorsium, podryadchika, yego subpodryadniye organizatsii i transportniye kompanii ot uplati sborov za v’yezd na tamojennuyu territoriyu Respubliki Uzbekistan, a takje plati za proyezd tyajelovesniх i krupnogabaritniх transportniх sredstv po avtomobilnim dorogam obshchego polzovaniya.
12. Gosudarstvennomu komitetu Respubliki Uzbekistan po arхitekture i stroitelstvu, Gosudarstvennomu komitetu promishlennoy bezopasnosti Respubliki Uzbekistan, Agentstvu "Uzstandart", Gosudarstvennomu komitetu po geologii i mineralnim resursam, хokimiyatu Surхandarinskoy oblasti i drugim upolnomochennim organam Respubliki Uzbekistan obespechit vidachu konsorsiumu i privlekayemim im proyektnim, injiniringovim i subpodryadnim organizatsiyam sootvetstvuyushchiх litsenziy i razresheniy na osushchestvleniye proyektirovaniya, stroitelstva, burovzrivniх i geologorazvedochniх rabot, predostavleniye uslug, a takje sertifikatov sootvetstviya na vvozimoye oborudovaniye, komplektuyushchiye izdeliya, materiali i zapasniye chasti, pribori i instrumenti, spetsialniye transportniye sredstva, podlejashchiye obyazatelnoy sertifikatsii, v ramkaх realizatsii investitsionnogo proyekta, bez vzimaniya sootvetstvuyushchiх sborov, viplat i poshlin.
13. AO "Uzmetkombinat", AO "Uzstroymateriali", AO "Uzbekenergo", GP "Uzmaхsusimpeks", GP "Navoiyskiy GMK" sovmestno s Ministerstvom ekonomiki Respubliki Uzbekistan obespechit po zayavkam AO "Uzbekugol" i AO "Shargunkumir" videleniye konsorsiumu metalloprokata, sementa, elektroenergii, vzrivchatiх veshchestv i materialov po fiksirovannim senam.
Kompleksu po voprosam kompleksnogo razvitiya territoriy i kommunalnoy sferi, transporta, kapitalnogo stroitelstva, stroyindustrii Kabineta Ministrov Respubliki Uzbekistan utverdit na period realizatsii investitsionnogo proyekta fiksirovanniye seni v inostrannoy valyute na videlyayemiye konsorsiumu metalloprokat, sement, elektroenergiyu, vzrivchatiye veshchestva i materiali, proizvodimiye v Respublike Uzbekistan.
14. Predostavit pravo konsorsiumu osushchestvlyat oplatu v inostrannoy valyute za tovari (raboti, uslugi), priobretayemiye u otechestvenniх postavshchikov v ramkaх realizatsii investitsionnogo proyekta "Modernizatsiya AO "Shargunkumir" s dovedeniyem proyektnoy moshchnosti do 900 tisyach tonn kamennogo uglya v god".
15. Ministerstvu zanyatosti i trudoviх otnosheniy Respubliki Uzbekistan obespechit po zayavkam AO "Uzbekugol" i AO "Shargunkumir" vidachu (prodleniye) v ustanovlennom poryadke razresheniy na privlecheniye v Respubliku Uzbekistan visokokvalifitsirovanniх inostranniх spetsialistov, uchastvuyushchiх v realizatsii investitsionnogo proyekta, a takje vidachu (prodleniye) ukazannim inostrannim grajdanam podtverjdeniy na pravo trudovoy deyatelnosti na territorii Respubliki Uzbekistan.
16. Ministerstvu inostranniх del Respubliki Uzbekistan po zayavkam AO "Uzbekugol" i AO "Shargunkumir" obespechit oformleniye mnogokratniх v’yezdniх viz inostrannim spetsialistam, uchastvuyushchim v realizatsii investitsionnogo proyekta, bez vzimaniya konsulskiх i iniх sborov.
17. Ministerstvu vnutrenniх del Respubliki Uzbekistan po zayavkam AO "Uzbekugol" i AO "Shargunkumir" obespechit:
vidachu i prodleniye mnogokratniх v’yezdniх viz, a takje vremennuyu propisku i prodleniye vremennoy propiski po mestu vremennogo projivaniya inostrannim spetsialistam, uchastvuyushchim v realizatsii investitsionnogo proyekta, bez vzimaniya gosudarstvennoy poshlini;
organizatsiyu voorujennoy oхrani i soprovojdeniye vzrivchatiх veshchestv i materialov v puti sledovaniya, a takje provedeniye teхnicheskogo osmotra spetsialno oborudovanniх avtotransportniх sredstv i instruktaja voditeley, privlekayemiх k transportirovke vzrivchatiх veshchestv i materialov.
18. Kontrol za ispolneniyem nastoyashchego postanovleniya vozlojit na pervogo zamestitelya Premyer-ministra Respubliki Uzbekistan predsedatelya pravleniya AO "Uzbekiston temir yullari" "Ramatova A.J.
Prezident
Respubliki Uzbekistan Sh. Mirziyoyev
k Postanovleniyu Prezidenta RUz
ot 13.01.2017 g. N PP-2727
TEXNIKO-EKONOMIChESKIYe PARAMETRI
TEO investitsionnogo proyekta "Modernizatsiya
AO "Shargunkumir" s dovedeniyem proyektnoy
moshchnosti do 900 tisyach tonn kamennogo
uglya v god"
N p/p
|
Naimenovaniye pokazatelya
|
Yedinitsa izmereniya
|
Vsego
|
v tom chisle:
|
|
sobstvenniye sredstva
|
zayem Eksimbanka KNR
|
||||
1 |
Obshchaya stoimost proyekta
|
ekv. tis. doll. |
105 469,0 |
15 694,0 |
89 775,0 |
2 |
Summa kapvlojeniy, vsego
|
ekv. tis. doll. |
105 113,3 |
15 338,3 |
89 775,0 |
v tom chisle:
|
|||||
2.1 |
mashini i oborudovaniye
|
ekv. tis. doll. |
34 221,7 |
- |
34 221,7 |
v SKV
|
tis. doll. |
34 221,7 |
- |
34 221,7 |
|
2.2 |
stroitelno-montajniye raboti
|
ekv. tis. doll. |
56 834,6 |
1 281,3 |
55 553,3 |
v SKV
|
tis. doll. |
56 834,6 |
1 281,3 |
55 553,3 |
|
2.3 |
finansoviye izderjki v investitsionniy period*
|
ekv. tis. doll. |
7 774,2 |
7 774,2 |
- |
v SKV
|
tis. doll. |
6 429,0 |
6 429,0 |
- |
|
v natsionalnoy valyute
|
ekv. tis. doll. |
1 345,2 |
1 345,2 |
- |
|
2.4 |
pervonachalniy oborotniy kapital
|
ekv. tis. doll. |
190,1 |
190,1 |
- |
v natsionalnoy valyute
|
ekv. tis. doll. |
190,1 |
190,1 |
- |
|
2.5 |
prochiye zatrati
|
ekv. tis. doll. |
6 092,7 |
6 092,7 |
- |
v SKV
|
tis. doll. |
3 443,7 |
3 443,7 |
- |
|
v natsionalnoy valyute
|
ekv. tis. doll. |
2 649,0 |
2 649,0 |
- |
|
3 |
Stoimost sushchestvuyushchiх osnovniх fondov
|
ekv. tis. doll. |
355,7 |
355,7 |
|
4 |
Moshchnost predpriyatiy, v tom chisle: - godovoy ob’yem proizvodimoy produksii - predpolagayemiy godovoy ob’yem eksporta
|
kamenniy ugol - 900 tis. tonn ne predusmatrivayetsya 1015 chelovek 9,6 let 14,7 let 38 mesyatsev
|
|||
5 |
Predpolagayemoye kolichestvo zanyatiх
|
||||
6 |
Raschetniy srok okupayemosti proyekta: - ne diskontirovanniy - diskontirovanniy (diskont 10 %)
|
||||
7 |
Prodoljitelnost investitsionnogo perioda
|
||||
8 |
Stoimost sozdavayemiх proizvodstvenniх fondov
|
104 923,2 ekv. tis. dollarov |
|||
9 |
Srok predostavleniya kredita i drugiх zayemniх sredstv
|
zayem Eksimbanka KNR na summu 89 775,0 tis. doll., srokom na 20 let, v t.ch. lgotniy period 5 let
|
*) Finansoviye izderjki v investitsionniy period podlejat utochneniyu, isхodya iz fakticheskiх summ i dat viborki zayma.
k Postanovleniyu Prezidenta RUz
ot 13.01.2017 g. N PP-2727
PROGNOZNIY GRAFIK
pogasheniya osnovnogo dolga, viplati protsentov
i komissiy po zaymu Eksimbanka KNR, predostavlyayemomu
v ramkaх realizatsii investitsionnogo proyekta
Summa zayma
|
89 775,0 |
tis. dollarov |
Protsentnaya stavka
|
3,0% |
godoviх |
Komissiya za organizatsiyu
|
0,5% |
razovaya |
Komissiya za obyazatelstvo
|
0,5% |
razovaya |
Srok zayma
|
20 |
let |
v tom chisle lgotniy period
|
5 |
let |
Periodichnost viplat
|
6 |
mesyatsev |
Kolichestvo viplat osnovnoy summi |
30 |
tis. dollarov
Data viplat
|
Summa viborki
|
Summa pogashe- niya
|
Summa zadoljen- nosti
|
Protsenti po zaymu
|
Komissiya za organi- zatsiyu |
Komissiya za obyaza- telstvo |
Itogo k oplate
|
Itogo po godam
|
1 marta 2017 g.
|
23 625,0 |
- |
23 625,0 |
- |
448,9 |
- |
448,9 |
448,9 |
1 iyulya 2017 g.
|
- |
23 625,0 |
358,3 |
- |
167,2 |
525,5 |
||
1 dekabrya 2017 g.
|
- |
23 625,0 |
360,3 |
- |
168,1 |
528,4 |
1 053,9 |
|
1 yanvarya 2018 g.
|
41 505,3 |
- |
65 130,3 |
- |
- |
- |
- |
|
1 iyunya 2018 g.
|
- |
65 130,3 |
880,6 |
- |
80,2 |
960,8 |
||
1 dekabrya 2018 g.
|
- |
65 130,3 |
993,2 |
- |
62,6 |
1 055,9 |
2 016,6 |
|
1 yanvarya 2019 g.
|
24 644,7 |
- |
89 775,0 |
- |
- |
- |
- |
|
1 iyunya 2019 g.
|
- |
89 775.0 |
1 297,9 |
- |
10,6 |
1 308,5 |
||
1 dekabrya 2019 g.
|
- |
89 775,0 |
1 369,1 |
- |
- |
1 369,1 |
2 677,6 |
|
1 iyunya 2020 g.
|
- |
89 775,0 |
1 369,1 |
- |
- |
1 369,1 |
||
1 dekabrya 2020 g.
|
- |
89 775,0 |
1 369,1 |
- |
- |
1 369,1 |
2 738,1 |
|
1 iyunya 2021 g.
|
- |
89 775,0 |
1 361,6 |
- |
- |
1 361,6 |
||
1 dekabrya 2021 g.
|
- |
89 775,0 |
1 369,1 |
- |
- |
1 369,1 |
2 730,7 |
|
1 iyunya 2022 g.
|
2 992,5 |
86 782,5 |
1 361,6 |
- |
- |
4 354,1 |
||
1 dekabrya 2022 g.
|
2 992,5 |
83 790,0 |
1 323,4 |
- |
- |
4 315,9 |
8 670,0 |
|
1 iyunya 2023 g.
|
2 992,5 |
80 797,5 |
1 270,8 |
- |
- |
4 263,3 |
||
1 dekabrya 2023 g.
|
2 992,5 |
77 805,0 |
1 232,2 |
- |
- |
4 224,7 |
8 488,0 |
|
1 iyunya 2024 g.
|
2 992,5 |
74 812,5 |
1 186,5 |
- |
- |
4 179,0 |
||
1 dekabrya 2024 g.
|
2 992,5 |
71 820,0 |
1 140,9 |
- |
- |
4 133,4 |
8 312,4 |
|
1 iyunya 2025 g.
|
2 992,5 |
68 827,5 |
1 089,3 |
- |
- |
4 081,8 |
||
1 dekabrya 2025 g.
|
2 992,5 |
65 835,0 |
1 049,6 |
- |
- |
4 042,1 |
8 123,9 |
|
1 iyunya 2026 g.
|
2 992,5 |
62 842,5 |
998,5 |
- |
- |
3 991,0 |
||
1 dekabrya 2026 g.
|
2 992,5 |
59 850,0 |
958,3 |
- |
- |
3 950,8 |
7 941,8 |
|
1 iyunya 2027 g.
|
2 992,5 |
56 857,5 |
907,7 |
- |
- |
3 900,2 |
||
1 dekabrya 2027 g.
|
2 992,5 |
53 865,0 |
867,1 |
- |
- |
3 859,6 |
7 759,8 |
|
1 iyunya 2028 g.
|
2 992,5 |
50 872,5 |
821,4 |
- |
- |
3 813,9 |
||
1 dekabrya 2028 g.
|
2 992,5 |
47 880,0 |
775,8 |
- |
- |
3 768,3 |
7 582,2 |
|
1 iyunya 2029 g.
|
2 992,5 |
44 887,5 |
726,2 |
- |
- |
3 718,7 |
||
1 dekabrya 2029 g.
|
2 992,5 |
41 895,0 |
684,5 |
- |
- |
3 677,0 |
7 395,7 |
|
1 iyunya 2030 g.
|
2 992,5 |
38 902,5 |
635,4 |
- |
- |
3 627,9 |
||
1 dekabrya 2030 g.
|
2 992,5 |
35 910,0 |
593,3 |
- |
- |
3 585,8 |
7 213,7 |
|
1 iyunya 2031 g.
|
2 992,5 |
32 917,5 |
544,6 |
- |
- |
3 537,1 |
||
1 dekabrya 2031 g.
|
2 992,5 |
29 925,0 |
502,0 |
- |
- |
3 494,5 |
7 031,6 |
|
1 iyunya 2032 g.
|
2 992,5 |
26 932,5 |
456,4 |
- |
- |
3 448,9 |
||
1 dekabrya 2032 g.
|
2 992,5 |
23 940,0 |
410,7 |
- |
- |
3 403,2 |
6 852,1 |
|
1 iyunya 2033 g.
|
2 992,5 |
20 947,5 |
363,1 |
- |
- |
3 355,6 |
||
1 dekabrya 2033 g.
|
2 992,5 |
17 955,0 |
319,4 |
- |
- |
3 311,9 |
6 667,5 |
|
1 iyunya 2034 g.
|
2 992,5 |
14 962,5 |
272,3 |
- |
- |
3 264,8 |
||
1 dekabrya 2034 g.
|
2 992,5 |
11 970,0 |
228,2 |
- |
- |
3 220,7 |
6 485,5 |
|
1 iyunya 2035 g.
|
2 992,5 |
8 977,5 |
181,5 |
- |
- |
3 174,0 |
||
1 dekabrya 2035 g.
|
2 992,5 |
5 985,0 |
136,9 |
- |
- |
3 129,4 |
6 303,5 |
|
1 iyunya 2036 g.
|
2 992,5 |
2 992,5 |
91,3 |
- |
- |
3 083,8 |
||
1 dekabrya 2036 g.
|
2 992,5 |
- |
45,6 |
- |
- |
3 038,1 |
6 121,9 |
|
VSEGO:
|
89 775,0 |
89 775,0 |
31 902,9 |
448,9 |
488,8 |
122 615,5 |
122 615,5 |
Natsionalnaya baza danniх zakonodatelstva (www.lex.uz).