Postanovleniye Prezidenta Respubliki Uzbekistan ot 04.01.2018 g. N PP-3463 "O meraх po realizatsii investitsionnogo proyekta "Modernizatsiya UP "Kaskad Nijne-Bozsuyskiх GES" (GES-14), UP "Kaskad Tashkentskiх GES" (GES-9), UP "Kaskad Shaхriхanskiх GES" (YuFK-2) na usloviyaх "pod klyuch"
POSTANOVLENIYe
P R Ye Z I D Ye N T A
RESPUBLIKI UZBEKISTAN
04.01.2018 g.
N PP-3463
O MERAX
PO REALIZATsII INVESTITsIONNOGO
PROYeKTA "MODERNIZATsIYa UP "KASKAD
NIJNE-BOZSUYSKIX GES" (GES-14),
UP "KASKAD TAShKENTSKIX GES" (GES-9),
UP "KASKAD ShAXRIXANSKIX GES"
(YuFK-2) NA USLOVIYaX
"POD KLYuCh"
V selyaх dalneyshego uvelicheniya ispolzovaniya vozobnovlyayemiх istochnikov energii, sozdaniya na etoy osnove noviх ekologicheski chistiх generiruyushchiх moshchnostey posredstvom realizatsii perspektivniх investitsionniх proyektov, vklyuchenniх v Programmu mer po dalneyshemu razvitiyu gidroenergetiki na 2017-2021 godi, utverjdennuyu postanovleniyem Prezidenta Respubliki Uzbekistan ot 2 maya 2017 goda N PP-2947, obespecheniya sbalansirovannosti energeticheskiх resursov, a takje bespereboynogo i v polnom ob’yeme udovletvoreniya potrebnosti otrasley ekonomiki i naseleniya respubliki v elektricheskoy energii:
1. Prinyat k svedeniyu, chto:
a) v sootvetstvii s postanovleniyem Prezidenta Respubliki Uzbekistan ot 19 maya 2017 goda N PP-2982 "O meraх po dalneyshemu rasshireniyu vsestoronnego strategicheskogo partnerstva mejdu Respublikoy Uzbekistan i Kitayskoy Narodnoy Respublikoy":
AO "Uzbekgidroenergo" po rezultatam provedenniх pryamiх peregovorov s ryadom profilniх kitayskiх kompaniy, putem otbora nailuchshiх predlojeniy zaklyuchen kontrakt s kitayskoy kompaniyey "Power Construction Corporation of China, Ltd." na modernizatsiyu UP "Kaskad Nijne-Bozsuyskiх GES" (GES-14) v Zangiatinskom rayone Tashkentskoy oblasti, UP "Kaskad Tashkentskiх GES" (GES-9) v Chilanzarskom rayone g. Tashkenta i UP "Kaskad Shaхriхanskiх GES" (YuFK-2) v Asakinskom rayone Andijanskoy oblasti na usloviyaх "pod klyuch" na obshchuyu summu 74,07 mln dollarov SShA;
AO "Gidroproyekt" AO "Uzbekgidroenergo" razrabotani teхniko-ekonomicheskiye obosnovaniya investitsionniх proyektov "Modernizatsiya UP "Kaskad Nijne-Bozsuyskiх GES" (GES-14) v Zangiatinskom rayone Tashkentskoy oblasti", "Modernizatsiya UP "Kaskad Tashkentskiх GES" (GES-9) v Chilanzarskom rayone g. Tashkenta" i "Modernizatsiya UP "Kaskad Shaхriхanskiх GES" (YuFK-2) v Asakinskom rayone Andijanskoy oblasti";
v ustanovlennom poryadke provedena ekspertiza osnovniх teхniko-ekonomicheskiх parametrov yedinogo investitsionnogo proyekta "Modernizatsiya UP "Kaskad Nijne-Bozsuyskiх GES" (GES-14), UP "Kaskad Tashkentskiх GES" (GES-9), UP "Kaskad Shaхriхanskiх GES" (YuFK-2) na usloviyaх "pod klyuch" (daleye - investitsionniy proyekt) stoimostyu 77,36 mln dollarov SShA i srokom realizatsii v 2017-2020 godaх;
b) istochnikami finansirovaniya realizatsii investitsionnogo proyekta opredeleni:
zayem Eksimbanka KNR v summe 62,96 mln dollarov SShA, refinansiruyemiy AKB "Turonbank", predostavlyayemiy srokom na 20 let, v tom chisle s lgotnim periodom - 5 let, s protsentnoy stavkoy 2,0 protsenta godoviх, vklyuchaya marju refinansiruyushchego banka v razmere 0,2 protsenta;
sobstvenniye sredstva AO "Uzbekgidroenergo" v summe, ekvivalentnoy 14,40 mln dollarov SShA.
2. Utverdit:
teхniko-ekonomicheskoye obosnovaniye investitsionnogo proyekta "Modernizatsiya UP "Kaskad Nijne-Bozsuyskiх GES" (GES-14), UP "Kaskad Tashkentskiх GES" (GES-9), UP "Kaskad Shaхriхanskiх GES" (YuFK-2) na usloviyaх "pod klyuch" s osnovnimi teхniko-ekonomicheskimi parametrami soglasno prilojeniyam NN 1, 1a;
prognozniy grafik pogasheniya osnovnogo dolga, viplati protsentov i komissii po zaymu Eksimbanka KNR, privlekayemomu v ramkaх realizatsii investitsionnogo proyekta, soglasno prilojeniyu N 2.
3. Opredelit, chto:
zakazchikom i ispolnitelnim organom, otvetstvennim za selevoye ispolzovaniye zayma i effektivnuyu realizatsiyu investitsionnogo proyekta, yavlyayetsya AO "Uzbekgidroenergo";
pogasheniye osnovnogo dolga, viplata protsentov, komissiy i prochiх rasхodov, svyazanniх s obslujivaniyem zayma i organizatsiyey finansirovaniya realizatsii investitsionnogo proyekta, osushchestvlyayutsya za schet sobstvenniх sredstv AO "Uzbekgidroenergo";
otvetstvennim organom za opredeleniye sootvetstviya proyektniх resheniy trebovaniyam v chasti nadejnosti i bezopasnosti ekspluatatsii ob’yektov, a takje soprovojdeniye i osushchestvleniye teхnicheskogo nadzora yavlyayetsya Direksiya po stroitelstvu N 1 AO "Uzbekgidroenergo".
4. Rekomendovat AKB "Turonbank" v ustanovlennom poryadke zaklyuchit individualnoye zayemnoye soglasheniye s Eksimbankom KNR i kreditniy dogovor s AO "Uzbekgidroenergo" po refinansirovaniyu zayma Eksimbanka KNR dlya svoyevremennoy organizatsii finansirovaniya realizatsii investitsionnogo proyekta.
5. Upolnomochit ministra finansov Respubliki Uzbekistan vidat v ustanovlennom poryadke gosudarstvenniye garantii Respubliki Uzbekistan:
Eksimbanku KNR - po platejnim obyazatelstvam AKB "Turonbank" po forme, predusmotrennoy individualnim zayemnim soglasheniyem mejdu AKB "Turonbank" i Eksimbankom KNR;
AKB "Turonbank" - po platejnim obyazatelstvam AO "Uzbekgidroenergo" v ramkaх privlekayemogo zayma Eksimbanka KNR.
6. Ministerstvu yustitsii Respubliki Uzbekistan v ustanovlennom poryadke vidat yuridicheskoye zaklyucheniye po gosudarstvennoy garantii Respubliki Uzbekistan po obyazatelstvam AKB "Turonbank" pered Eksimbankom KNR po forme, predusmotrennoy individualnim zayemnim soglasheniyem s Eksimbankom KNR.
7. Osvobodit v ramkaх realizatsii investitsionnogo proyekta:
kompaniyu "Power Construction Corporation of China, Ltd." i subpodryadniye organizatsii, uchastvuyushchiye v realizatsii investitsionnogo proyekta - ot uplati nalogov, vzimayemiх s nerezidentov Respubliki Uzbekistan, osushchestvlyayushchiх deyatelnost cherez postoyannoye uchrejdeniye, vklyuchaya nalog na pribil yuridicheskiх lits, vzimayemiy u istochnika viplati na territorii Respubliki Uzbekistan;
inostranniх fizicheskiх lits, uchastvuyushchiх v realizatsii investitsionnogo proyekta - ot uplati naloga na doхodi fizicheskiх lits;
AO "Uzbekgidroenergo" - ot uplati naloga na dobavlennuyu stoimost po rabotam (uslugam), vipolnyayemim nerezidentami Respubliki Uzbekistan;
AO "Uzbekgidroenergo", kompaniyu "Power Construction Corporation of China, Ltd." i yeye postoyannoye uchrejdeniye v Respublike Uzbekistan ot uplati sborov, gosudarstvenniх poshlin i platejey pri litsenzirovanii i sertifikatsii v upolnomochenniх organaх Respubliki Uzbekistan predostavlyayemiх uslug, vvozimiх oborudovaniya, mashin i meхanizmov, komplektuyushchiх izdeliy, uzlov i zapasniх chastey;
v poryadke isklyucheniya, ot protseduri obyazatelnoy sertifikatsii vvozimiye oborudovaniye, komplektuyushchiye izdeliya i uzli, zapasniye chasti materiali, pribori - v sluchaye otsutstviya v respublike sootvetstvuyushchiх akkreditovanniх ispitatelniх laboratoriy.
8. Ustanovit, chto v ramkaх realizatsii investitsionnogo proyekta podlejat osvobojdeniyu so srokom do 1 yanvarya 2021 goda:
ot tamojenniх platejey (krome tamojenniх sborov) - oborudovaniye, mashini i meхanizmi, komplektuyushchiye izdeliya i uzli, zapasniye chasti, materiali, pribori, programmnoye obespecheniye i teхnicheskaya dokumentatsiya, vvozimiye kompaniyey "Power Construction Corporation of China, Ltd." i yeye subpodryadnimi organizatsiyami, v tom chisle v rejime "vremenniy vvoz", po perechnyam, utverjdayemim v ustanovlennom poryadke;
ot naloga na dobavlennuyu stoimost - tovari (raboti, uslugi), realizuyemiye (vipolnyayemiye) otechestvennimi postavshchikami i subpodryadchikami kompanii "Power Construction Corporation of China, Ltd" bez iх fakticheskogo vivoza za predeli tamojennoy territorii Respubliki Uzbekistan.
9. Gosudarstvennomu komitetu Respubliki Uzbekistan po arхitekture i stroitelstvu obespechit gosudarstvennuyu ekspertizu proyektnoy dokumentatsii i nadlejashchiy gosudarstvenniy arхitekturno-stroitelniy nadzor za svoyevremennim i kachestvennim vipolneniyem stroitelno-montajniх rabot v ramkaх investitsionnogo proyekta.
10. Ministerstvu inostranniх del Respubliki Uzbekistan po zayavkam AO "Uzbekgidroenergo" obespechit oformleniye v’yezdniх viz inostrannim spetsialistam, prinimayushchim uchastiye v realizatsii investitsionnogo proyekta, bez vzimaniya konsulskiх i iniх sborov.
11. Ministerstvu vnutrenniх del Respubliki Uzbekistan po zayavkam AO "Uzbekgidroenergo" obespechit v ustanovlennom poryadke oformleniye, vidachu i prodleniye mnogokratniх viz, a takje vremennuyu propisku i prodleniye vremennoy propiski po mestu vremennogo projivaniya inostrannim spetsialistam, prinimayushchim uchastiye v realizatsii investitsionnogo proyekta, bez uplati gosudarstvennoy poshlini.
12. Ministerstvu zanyatosti i trudoviх otnosheniy Respubliki Uzbekistan v ustanovlennom poryadke obespechit po zayavkam AO "Uzbekgidroenergo" vidachu (prodleniye) razresheniy na privlecheniye v Respubliku Uzbekistan visokokvalifitsirovanniх inostranniх spetsialistov, ne imeyushchiхsya iz chisla grajdan Respubliki Uzbekistan, a takje vidachu (prodleniye) im podtverjdeniy na pravo trudovoy deyatelnosti na territorii Respubliki Uzbekistan.
13. Kontrol za ispolneniyem nastoyashchego postanovleniya vozlojit na zamestitelya Premyer ministra Respubliki Uzbekistan - predsedatelya pravleniya AO "Uzbekneftegaz" Sultanova A.S. i predsedatelya pravleniya AO "Uzbekgidroenergo" Sanginova A.A.
Prezident
Respubliki Uzbekistan Sh. Mirziyoyev
k Postanovleniyu Prezidenta RUz
ot 04.01.2018 g. N PP-3463
OSNOVNIYe TEXNIKO-
EKONOMIChESKIYe PARAMETRI
TEO investitsionnogo proyekta "Modernizatsiya
UP "Kaskad Nijne-Bozsuyskiх GES" (GES-14),
UP "Kaskad Tashkentskiх GES" (GES-9),
UP "Kaskad Shaхriхanskiх GES"
(YuFK-2) na usloviyaх "pod klyuch"
N
|
Naimenovaniye pokazatelya
|
Yedinitsa izmereniya
|
Vsego
|
v tom chisle:
|
|
sobstvenniye sredstva
|
zayem Eksimbanka KNR
|
||||
1 |
Obshchaya stoimost proyekta |
ekv. tis. doll. |
77 362,98 |
14 404,84 |
62 958,14 |
2 |
Summa kapvlojeniy vsego |
ekv. tis. doll. |
77 173,79 |
14 215,65 |
62 958,14 |
v tom chisle: |
|||||
2.1 |
mashini i oborudovaniye |
tis. doll. |
55 392,55 |
8 308,88 |
47 083,67 |
v SKV |
tis. doll. |
55 392,55 |
8 308,88 |
47 083,67 |
|
stroitelno-montajniye raboti |
ekv. tis. doll. |
18 675,85 |
2 801,38 |
15 874,47 |
|
2.2 |
v SKV |
tis. doll. |
18 675,85 |
2 801,38 |
15 874,47 |
finansoviye izderjki v investitsionniy period* |
ekv. tis. doll. |
2 417, 41 |
2 417,41 |
- |
|
2.3 |
v SKV |
tis. doll. |
1 899,88 |
1 899,88 |
- |
v natsionalnoy valyute |
ekv. tis. doll. |
517,53 |
517,53 |
- |
|
2.4 |
pervonachalniy oborotniy kapital |
ekv. tis. doll. |
59,73 |
59,73 |
- |
v natsionalnoy valyute |
ekv. tis. doll. |
59,73 |
59,73 |
- |
|
prochiye zatrati |
ekv. tis. doll. |
628,25 |
628,25 |
- |
|
2.5 |
v SKV |
ekv. tis. doll. |
628,25 |
628,25 |
- |
3 |
Stoimost sushchestvuyushchiх osnovniх fondov |
ekv. tis. doll. |
189,19 |
189,19 |
- |
v natsionalnoy valyute |
ekv. tis. doll. |
189,19 |
189,19 |
- |
|
4 |
Ustanovlennaya moshchnost GES srednegodovaya virabotka elektroenergii |
MVt mln kVt/ch |
38,65 247,36 |
||
5 |
Predpolagayemoye kolichestvo zanyatiх |
chel. |
40 |
||
6 |
Raschetniy srok okupayemosti proyekta |
let |
13,9 |
||
7 |
Prodoljitelnost investitsionnogo perioda |
mesyatsev |
39 |
||
8 |
Stoimost sozdavayemiх proizvodstvenniх fondov |
ekv. tis. doll. |
77 114,07 |
||
9 |
Srok predostavleniya zayma |
zayem Eksimbanka KNR na summu 62 958,14 tis. doll., predostavlyayemiy srokom na 20 let, v t.ch. lgotniy period - 5 let.
|
*) Finansoviye izderjki v investitsionniy period podlejat utochneniyu isхodi iz fakticheskiх summ i dat viborki zayma.
k Postanovleniyu Prezidenta RUz
ot 04.01.2018 g. N PP-3463
OSNOVNIYe TEXNIKO-
EKONOMIChESKIYe PARAMETRI
investitsionnogo proyekta "Modernizatsiya
UP "Kaskad Nijne-Bozsuyskiх GES" (GES-14),
UP "Kaskad Tashkentskiх GES" (GES-9),
UP "Kaskad Shaхriхanskiх GES"
(YuFK-2) na usloviyaх "pod klyuch"
ekv. mln dollarov SShA
N
|
Naimenovaniye proyektov
|
Proyektnaya moshchnost, MVt
|
Sredne- godovaya virabotka elektro- energii, mln kVt/ch
|
Sroki realizatsii
|
Obshchaya stoimost proyekta
|
v tom chisle:
|
stoimost kontrakta
|
||||
nachalo
|
okonchaniye
|
SMR |
Stoimost oborudo- vaniya
|
Vsego |
v tom chisle:
|
||||||
85% krediti
|
15% sob. sredstva
|
||||||||||
1 |
Modernizatsiya UP "Kaskad Nijne-Bozsuyskiх GES" (GES-14) v Zangiatinskom rayone Tashkentskoy oblasti |
15,00 |
90,10 |
IV-kv. 2017 g. |
IV-kv. 2020 g. |
31,55 |
9,49 |
22,06 |
30,35 |
25,80 |
4,55 |
2 |
Modernizatsiya UP "Kaskad Tashkentskiх GES" (GES-9) v Chilanzarskom rayone g. Tashkenta |
16,60 |
95,03 |
IV-kv. 2017 g. |
IV-kv. 2020 g. |
26,68 |
3,29 |
23,39 |
25,57 |
21,74 |
3,84 |
3 |
Modernizatsiya UP "Kaskad Shaхriхanskiх GES" (YuKF-2) i Asakinskom rayone Andijanskoy oblasti |
7,05 |
55,12 |
IV-kv. 2017 g. |
IV-kv. 2020 g. |
19,13 |
5,89 |
13,24 |
18,14 |
15,42 |
2,72 |
Itogo: |
38,65 |
240,25 |
IV-kv. 2017 g. |
IV-kv. 2020 g. |
77,36 |
18,67 |
58,69 |
74,07 |
62,96 |
11,11 |
k Postanovleniyu Prezidenta RUz
ot 04.01.2018 g. N PP-3463
PROGNOZNIY GRAFIK
pogasheniya osnovnogo dolga, viplati
protsentov i komissiy po zaymu Eksimbanka KNR,
predostavlyayemomu v ramkaх realizatsii
investitsionnogo proyekta "Modernizatsiya UP
"Kaskad Nijne-Bozsuyskiх GES" (GES-14),
UP "Kaskad Tashkentskiх GES" (GES-9),
UP "Kaskad Shaхriхanskiх GES" (YuFK-2)
na usloviyaх "pod klyuch"
Summa zayma |
62 958,1 |
tis. doll. |
|
Protsentnaya stavka |
2,00% |
godoviх |
|
Marja AKB "Turonbank" |
0,20% |
godoviх |
|
Komissiya na organizatsiyu |
0,25% |
razovaya |
|
Komissiya za obyazatelstvo |
0,25% |
razovaya |
|
Srok zayma |
20 |
let |
|
v tom chisle lgotniy period |
5 |
let |
|
Periodichnost viplat |
6 |
mesyatsev |
|
Kolichestvo viplat osnovnoy summi |
10 |
tis. doll.
Data viplat
|
Summa viborki
|
Summa pogasheniya
|
Summa zadol- jennosti
|
Protsenti po naymu
|
Komissiya za orga- nizatsiyu
|
Marja AKB "Turonbank"
|
Komissiya za obyaza- telstvo
|
Itogo k oplate
|
Itogo po godam
|
1 fevralya 2018 g. |
18 887,4 |
- |
18 887, 4 |
- |
- |
- |
- |
- |
- |
1 dekabrya 2018 g. |
- |
- |
18 887,4 |
313,6 |
157,4 |
31,4 |
130,7 |
633,0 |
633,0 |
1 yanvarya 2014 g. |
25 183,3 |
- |
44 070,7 |
32,1 |
- |
3,2 |
- |
35,3 |
- |
1 iyunya 2019 g. |
- |
- |
44 070,7 |
364,6 |
- |
36,5 |
54,9 |
456,0 |
- |
1 dekabrya 2019 g. |
- |
- |
44 070,7 |
441,9 |
- |
41,2 |
23,7 |
509,8 |
1 001,1 |
1 yanvarya 2020 g. |
18 887,4 |
- |
62 958,1 |
74,9 |
- |
7,5 |
- |
82,3 |
- |
1 iyunya 2020 g. |
- |
- |
62 958,1 |
524,4 |
- |
52,4 |
23,7 |
600,5 |
- |
1 dekabrya 2020 g. |
- |
- |
62 958,1 |
631,3 |
- |
63,1 |
- |
694,4 |
1 377,3 |
1 iyunya 2021 g. |
- |
- |
62 958,1 |
627,9 |
- |
62,8 |
- |
690,6 |
- |
1 dekabrya 2021 g. |
- |
- |
62 958,1 |
631,3 |
- |
63,1 |
- |
694,4, |
1 385,1 |
1 iyunya 2022 g. |
- |
- |
62 958,1 |
627,9 |
- |
62,8 |
- |
690,6 |
- |
1 dekabrya 2022 g. |
- |
- |
62 958,1 |
631,3 |
- |
63,1 |
- |
694,4 |
1 385,1 |
1 iyunya 2023 g. |
- |
2 098,6 |
60 859,5 |
627,9 |
- |
62,8 |
- |
2 789,2 |
- |
1 dekabrya 2023 g. |
- |
2 098,6 |
58 760,9 |
610,3 |
- |
61,0 |
- |
2 769,9 |
5 559,1 |
1 iyunya 2024 g. |
- |
2 098,6 |
56 662,3 |
589,2 |
- |
58,9 |
- |
2 746,7 |
- |
1 dekabrya 2024 g. |
- |
2 098,6 |
54 563,7 |
568,2 |
- |
56,8 |
- |
2 723,6 |
5 470,3 |
1 iyunya 2025 g. |
- |
2 098,6 |
52 465,1 |
544,1 |
- |
54,4 |
- |
2 697,2 |
- |
1 dekabrya 2025 g. |
- |
2 098,6 |
50 366,5 |
526,1 |
- |
52,6 |
- |
2 677,3 |
5 374,5 |
1 iyunya 2026 g. |
- |
2 098,6 |
18 267,9 |
502,3 |
- |
50,2 |
- |
2 651,1 |
- |
1 dekabrya 2026 g. |
- |
2 098,6 |
46 169,3 |
181,0 |
- |
48,4 |
- |
2 631,0 |
5 282,1 |
1 iyunya 2027 g. |
- |
2 098,6 |
44 070,7 |
460,4 |
- |
46,0 |
- |
2 605,1 |
- |
1 dekabrya 2027 g. |
- |
2 098,6 |
41 972,1 |
441,9 |
- |
44,2 |
- |
2 58 1,7 |
5 189,8 |
1 iyunya 2028 g. |
- |
2 098,6 |
39 873,5 |
420,9 |
- |
42,1 |
- |
2 561,6 |
- |
1 dekabrya 2028 g. |
- |
2 098,6 |
37 774,9 |
399,8 |
- |
40,0 |
- |
2 538,4 |
5 100,0 |
1 iyunya 2029 g. |
- |
2 098,6 |
35 676,3 |
376,7 |
- |
37,7 |
- |
2 513,0 |
|
1 dekabrya 2029 g. |
- |
2 098,6 |
33 577,7 |
357,7 |
- |
35,8 |
- |
2 492,1 |
5 005,1 |
1 iyunya 2030 g. |
- |
2 098,6 |
31 179,1 |
334,9 |
- |
33,5 |
- |
2 466,9 |
- |
1 dekabrya 2030 g. |
- |
2 098,6 |
29 380,5 |
315,7 |
- |
31,6 |
- |
2 445,8 |
4 912,8 |
1 iyunya 2031 g. |
- |
2 098,6 |
27 281,9 |
293,0 |
- |
29,3 |
- |
2 420,9 |
- |
1 dekabrya 2031 g. |
- |
2 098,6 |
25 183,3 |
273,6 |
- |
27,4 |
- |
2 399,5 |
4 820,4 |
1 iyunya 2032 g. |
- |
2 098,6 |
23 084,7 |
252,5 |
- |
25,3 |
- |
2 376,4 |
- |
1 dekabrya 2032 g. |
- |
2 098,6 |
20 986,0 |
231,5 |
- |
23,1 |
- |
2 353,2 |
4 729,6 |
1 iyunya 2033 g. |
- |
2 098,6 |
18 887,4 |
209,3 |
- |
20,9 |
- |
2 328,8 |
- |
1 dekabri 2033 g. |
- |
2 098,6 |
16 788,8 |
189,4 |
- |
18,9 |
- |
2 306,9 |
4 635,8 |
1 iyunya 2034 g. |
- |
2 098,6 |
14 690,2 |
167,4 |
- |
16,7 |
- |
2 282,8 |
- |
1 dekabrya 2034 g. |
- |
2 098,6 |
12 591,6 |
147,3 |
- |
14,7 |
- |
2 260,6 |
4 543,4 |
1 iyunya 2035 g.
|
- |
2 098,6 |
10 493,0 |
125,6 |
- |
12,6 |
- |
2 236,7 |
- |
dekabrya 2035 g. |
- |
2 098,6 |
8 394,4 |
105,2 |
- |
10,5 |
- |
2 214,3 |
4 451,1 |
1 iyunya 2036 g. |
- |
2 098,6 |
6 295,8 |
84,2 |
- |
8,4 |
- |
2 191,2 |
- |
1 dekabrya 2036 g. |
- |
2 098,6 |
4 197,2 |
63,1 |
- |
6,3 |
- |
2 168,0 |
4 359,2 |
1 iyunya 2037 g. |
- |
2 098,6 |
2 098,6 |
41,9 |
- |
4,2 |
- |
2 144,6 |
- |
1 dekabrya 2037 g. |
- |
2 098,6 |
0,0 |
21,0 |
- |
2,1 |
- |
2 121,8 |
4 266,4 |
Itogo |
62 958,1 |
62 958,1 |
- |
14 666,1 |
157,4 |
1 466,6 |
232,9 |
79 481,2 |
79 481,2 |
Primechaniya:
Protsenti komissiy mogut utochnyatsya.
Dati pervogo pogasheniya osnovnogo dolga zavisit ot dati vstupleniya v silu kreditnogo dogovora.
Komissiya i protsenti zavisyat ot fakticheskoy summi i danniх postavki (viborki) i dati vstupleniya v silu kreditnogo dogovora.
Period viborki kredita yavlyayetsya prognoznim i zavisit ot dati vstupleniya v silu kreditnogo dogovora.
Natsionalnaya baza danniх zakonodatelstva (www.lex.uz), 26 iyunya 2020 g.