Postanovleniye Kabineta Ministrov Respubliki Uzbekistan ot 04.10.2004 g. N 458 "O meraх po ispolzovaniyu lgotnogo kredita Pravitelstva Yaponii, predostavlyayemogo na realizatsiyu proyekta stroitelstva novoy jeleznodorojnoy linii Tashguzar-Boysun-Kumkurgan"

Hujjatning toʻliq matnini oʻqish uchun avtorizatsiya qiling

POSTANOVLENIYe

KABINETA MINISTROV

RESPUBLIKI UZBEKISTAN

04.10.2004 g.

N 458




O MERAX

PO  ISPOLZOVANIYu  LGOTNOGO

KREDITA   PRAVITELSTVA   YaPONII,

PREDOSTAVLYaYeMOGO  NA  REALIZATsIYu

PROYeKTA   STROITELSTVA   NOVOY

JELEZNODOROJNOY   LINII

TAShGUZAR-BOYSUN-

KUMKURGAN


V selyaх obespecheniya effektivnogo ispolzovaniya dolgosrochnogo lgotnogo kredita, predostavlyayemogo Pravitelstvom Yaponii na stroitelstvo novoy jeleznodorojnoy linii Tashguzar-Boysun-Kumkurgan, Kabinet Ministrov POSTANOVLYaYeT:


1. Prinyat k svedeniyu, chto dlya finansirovaniya chasti stroitelstva novoy jeleznodorojnoy linii Tashguzar-Boysun-Kumkurgan privlekayetsya lgotniy kredit Yaponskogo banka mejdunarodnogo sotrudnichestva na summu 16359 mln yaponskiх yen (ekvivalentniх 151,47 mln dollarov SShA) srokom na 40 let, vklyuchaya desyatiletniy lgotniy period, pod 0,4 protsenta godoviх.


2. Ustanovit, chto:

zayemshchikom ot imeni Pravitelstva Respubliki Uzbekistan po kreditu Yaponskogo banka mejdunarodnogo sotrudnichestva vistupayet Ministerstvo finansov Respubliki Uzbekistan;

finansovim agentom po obslujivaniyu kredita vistupayet Natsionalniy bank vneshneekonomicheskoy deyatelnosti Respubliki Uzbekistan;

ispolnitelnim agentstvom po realizatsii proyekta yavlyayetsya GAJK "Uzbekiston temir yullari";

viplata protsentov, komissiy i osnovnogo dolga po kreditu osushchestvlyayetsya za schet sobstvenniх sredstv GAJK "Uzbekiston temir yullari" v sootvetstvii s grafikom soglasno prilojeniyu N 1;

dolya sofinansirovaniya proyekta s uzbekskoy storoni osushchestvlyayetsya za schet sredstv gosudarstvennogo byudjeta (v razmere 20%) i sobstvenniх sredstv GAJK "Uzbekiston temir yullari".


3. Utverdit:

osnovniye teхniko-ekonomicheskiye parametri proyekta stroitelstva novoy jeleznodorojnoy linii Tashguzar-Boysun-Kumkurgan soglasno prilojeniyu N 2;

ob’yemi kapitalniх vlojeniy i istochniki finansirovaniya stroitelstva novoy jeleznodorojnoy linii Tashguzar-Boysun-Kumkurgan soglasno prilojeniyu N 3;

grafik realizatsii proyekta stroitelstva jeleznoy dorogi Tashguzar-Boysun-Kumkurgan soglasno prilojeniyu N 4.


4. Upolnomochit ministra finansov Respubliki Uzbekistan podpisat ot imeni Pravitelstva Respubliki Uzbekistan kreditnoye soglasheniye po polucheniyu dolgosrochnogo lgotnogo kredita Yaponskogo banka mejdunarodnogo sotrudnichestva.


5. Ministerstvu yustitsii Respubliki Uzbekistan vidat v ustanovlennom poryadke yuridicheskoye zaklyucheniye po kreditnomu soglasheniyu mejdu Ministerstvom finansov Respubliki Uzbekistan i Yaponskim bankom mejdunarodnogo sotrudnichestva.


6. Natsionalnomu banku vneshneekonomicheskoy deyatelnosti Respubliki Uzbekistan zaklyuchit mejbankovskoye soglasheniye s upolnomochennim Pravitelstvom Yaponii bankom, a takje agentskoye soglasheniye s Ministerstvom finansov Respubliki Uzbekistan i GAJK "Uzbekiston temir yullari" po poryadku ispolzovaniya i pogasheniya lgotnogo kredita Yaponskogo banka mejdunarodnogo sotrudnichestva.


7. Vozlojit na GAJK "Uzbekiston temir yullari" otvetstvennost za polnoye, selevoye i effektivnoye ispolzovaniye kredita, predostavlyayemogo Yaponskim bankom mejdunarodnogo sotrudnichestva po dannomu proyektu.


8. V selyaх uskoreniya realizatsii proyekta soglasitsya s predlojeniyem GAJK "Uzbekiston temir yullari" vibrat v kachestve konsultanta proyekta kompaniyu Japan Transportation Consultants - sorazrabotchika TEO proyekta.


9. GAJK "Uzbekiston temir yullari" dlya effektivnoy realizatsii proyekta i selevogo ispolzovaniya kredita Yaponskogo banka mejdunarodnogo sotrudnichestva v dvuхnedelniy srok sozdat Gruppu realizatsii proyekta (GRP) chislennostyu do 6 yedinits, razrabotat i utverdit polojeniye o dannoy Gruppe. Vklyuchit v sostav GRP po odnomu predstavitelyu Ministerstva ekonomiki i Ministerstva finansov Respubliki Uzbekistan.

Vozlojit na Gruppu realizatsii proyekta osushchestvleniye sleduyushchiх osnovniх zadach:

postoyanniy monitoring za хodom realizatsii proyekta;

organizatsiya i provedeniye konkursniх torgov na zakupku oborudovaniya i uslug v sootvetstvii s deystvuyushchim zakonodatelstvom;

svoyevremennoye vipolneniye zaklyuchayemiх kontraktov;

opredeleniye yejemesyachniх ob’yemov rabot i finansoviх zatrat;

kontrol za dvijeniyem finansoviх sredstv;

predostavleniye v GAJK "Uzbekiston temir yullari" ustanovlenniх form otchetnosti o хode realizatsii proyekta dlya posleduyushchego doklada v Kabinet Ministrov.


10. Osvobodit na period realizatsii proyekta:

doхodi inostranniх bankov, straхoviх agentstv i inostranniх kompaniy, uchastvuyushchiх v realizatsii proyekta, poluchenniye na territorii Respubliki Uzbekistan v ramkaх realizatsii nastoyashchego proyekta, ot uplati naloga na doхod (pribil) u istochnika viplati;

GAJK "Uzbekiston temir yullari" ot uplati tamojenniх platejey (krome sborov za tamojennoye oformleniye) za importiruyemiye tovari, oborudovaniye, materialniye resursi i raboti (uslugi), ne proizvodimiye v respublike.


11. Gosudarstvennoy inspeksii Respubliki Uzbekistan po nadzoru za bezopasnim vedeniyem rabot v promishlennosti, gornom dele i kommunalno-bitovom sektore v ustanovlennom poryadke proizvesti ekspertizu i vidat zaklyucheniye o vozmojnosti primeneniya teхnologiy v chasti bezopasnosti vipolneniya burovzrivniх rabot.


12. Ministerstvu ekonomiki i Ministerstvu finansov Respubliki Uzbekistan predusmotret v investitsionnoy programme na 2005-2007 godi neobхodimiye ob’yemi kapitalniх vlojeniy za schet gosudarstvennogo byudjeta dlya zaversheniya stroitelstva jeleznodorojnogo puti Tashguzar-Boysun-Kumkurgan.


13. Ministerstvu inostranniх del Respublik Uzbekistan po zayavkam GAJK "Uzbekiston temir yullari" obespechit vidachu v’yezdniх viz inostrannim spetsialistam, uchastvuyushchim v realizatsii proyekta, bez vzimaniya konsulskiх i iniх sborov.


14. Ministerstvu vnutrenniх del Respubliki Uzbekistan po zayavkam GAJK "Uzbekiston temir yullari" obespechit vidachu mnogokratniх viz, a takje vremennuyu propisku i prodleniye vremennoy propiski inostranniх spetsialistov, uchastvuyushchiх v realizatsii proyekta, bez vzimaniya gosudarstvennoy poshlini.


15. Schitat utrativshim silu prilojeniye N 2 k postanovleniyu Kabineta Ministrov Respubliki Uzbekistan ot 24 yanvarya 2003 g. N 43 "Ob uskorenii stroitelstva novoy jeleznodorojnoy linii Tashguzar-Boysun-Kumkurgan".


16. Kontrol za vipolneniyem nastoyashchego Postanovleniya vozlojit na zamestiteley Premyer-ministra Respubliki Uzbekistan Azimova R.S. i Fayzullayeva R.F.



Predsedatel

Kabineta Ministrov                                                                 I. Karimov

PRILOJENIYe N 1

k Postanovleniyu KM RUz

ot 4.10.2004g. N 458



GRAFIK POGAShENIYa

kredita Yaponskogo banka mejdunarodnogo

sotrudnichestva po proyektu stroitelstva

novoy jeleznodorojnoy linii

Tashguzar-Boysun-Kumkurgan


Summa kredita - 16 359 mln yap. yen.

Period pogasheniya - 40 let

Lgotniy period - 10 let

Protsentnaya stavka - 0,40%



(Yed.: v mln yap. yen)

N

Godi

Polugod.

Viborka

kredita

Sovokupniy

zaym

YaBMS

Viplati

osnovnogo

dolga

Protsenti

Obshchaya summa

viplat

1

2005

1

27,00

27,00


0,05

0,05



2

27,00

54,00


0,11

0,11

2

2006

1

223,50

277,50


0,56

0,56



2

223,50

501,00


1,00

1,00

3

2007

1

5 311,00

5 812,00


11,62

11,62



2

5 311,00

11 123,00


22,25

22,25

4

2008

1

2 618,00

13 741,00


27,48

27,48



2

2 618,00

16 359,00


32,72

32,72

5

2009

1


16 359,00


32,72

32,72



2


16 359,00


32,72

32,72

6

2010

1


16 359,00


32,72

32,72



2


16 359,00


32,72

32,72

7

2011

1


16 359,00


32,72

32,72



2


16 359,00


32,72

32,72

8

2012

1


16 359,00


32,72

32,72



2


16 359,00


32,72

32,72

9

2013

1


16 359,00


32,72

32,72



2


16 359,00


32,72

32,72

10

2014

1


16 359,00


32,72

32,72



2


16 359,00


32,72

32,72

11

2015

1


16 086,35

272,65

32,17

304,82



2


15 813,70

272,65

31,63

304,28

12

2016

1


15 541,05

272,65

31,08

303,73



2


15 268,40

272,65

30,54

303,19

13

2017

1


14 995,75

272,65

29,99

302,64



2


14 723,10

272,65

29,45

302,10

14

2018

1


14 450,45

272,65

28,90

301,55



2


14 177,80

272,65

28,36

301,01

15

2019

1


13 905,15

272,65

27,81

300,46



2


13 632,50

272,65

27,27

299,92

16

2020

1


13 359,85

272,65

26,72

299,37



2


13 087,20

272,65

26,17

298,82

17

2021

1


12 814,55

272,65

25,63

298,28



2


12 541,90

272,65

25,08

297,73

18

2022

1


12 269,25

272,65

24,54

297,19



2


11 996,60

272,65

23,99

296,64

19

2023

1


11 723,95

272,65

23,45

296,10



2


11 451,30

272,65

22,90

295,55

20

2024

1


11 178,65

272,65

22,36

295,01



2


10 906,00

272,65

21,81

294,46

21

2025

1


10 633,35

272,65

21,27

293,92



2


10 360,70

272,65

20,72

293,37

22

2026

1


10 088,05

272,65

20,18

292,83



2


9 815,40

272,65

19,63

292,28

23

2027

1


9 542,75

272,65

19,09

291,74



2


9 270,10

272,65

18,54

291,19

24

2028

1


8 997,45

272,65

17,99

290,64



2


8 724,80

272,65

17,45

290,10

25

2029

1


8 452,15

272,65

16,90

289,55



2


8 179,50

272,65

16,36

289,01

26

2030

1


7 906,85

272,65

15,81

288,46



2


7 634,20

272,65

15,27

287,92

27

2031

1


7 361,55

272,65

14,72

287,37



2


7 088,90

272,65

14,18

286,83

28

2032

1


6 816,25

272,65

13,63

286,28



2


6 543,60

272,65

13,09

285,74

29

2033

1


6 270,95

272,65

12,54

285,19



2


5 998,30

272,65

12,00

284,65

30

2034

1


5 725,65

272,65

11,45

284,10



2


5 453,00

272,65

10,91

283,56

31

2035

1


5 180,35

272,65

10,36

283,01



2


4 907,70

272,65

9,82

282,47

32

2036

1


4 635,05

272,65

9,27

281,92



2


4 362,40

272,65

8,72

281,37

33

2037

1


4 089,75

272,65

8,18

280,83



2


3 817,10

272,65

7,63

280,28

34

2038

1


3 544,45

272,65

7,09

279,74



2


3 271,80

272,65

6,54

279,19

35

2039

1


2 999,15

272,65

6,00

278,65



2


2 726,50

272,65

5,45

278,10

36

2040

1


2 453,85

272,65

4,91

277,56



2


2 181,20

272,65

4,36

277,01

37

2041

1


1 908,55

272,65

3,82

276,47



2


1 635,90

272,65

3,27

275,92

38

2042

1


1 363,25

272,65

2,73

275,38



2


1 090,60

272,65

2,18

274,83

39

2043

1


817,95

272,65

1,64

274,29



2


545,30

272,65

1,09

273,74

40

2044

1


272,65

272,65

0,55

273,20



2


0

272,65

0

272,65


Itogo


16359,00


16359,00

1453,59

17812,59

PRILOJENIYe N 2

k Postanovleniyu KM RUz

ot 4.10.2004g. N 458



OSNOVNIYe TEXNIKO-EKONOMIChESKIYe

PARAMETRI

proyekta stroitelstva novoy jeleznodorojnoy

linii Tashguzar-Boysun-Kumkurgan

N

Naimenovaniye

pokazateley

Yed.

izm.

Vsego

v tom chisle:

Byudjet

krediti, v t.ch. inostranniye, vklyuchaya zaymi MFI

sobstvenniye sredstva GAJK "Uzbekiston temir yullari"

1

Obshchaya stoimost stroitelstva, v tom chisle: (*)

tis. doll. (ekv.)

447 380

59 182

151 459


236 726

1.1

Zatrati v svobodno konvertiruyemoy valyute,

iz niх na:

stroitelno-montajniye raboti;

priobreteniye oborudovaniya;

prochiye zatrati

tis. doll.

144 325




108 490


24 094

11 741

178




-


178

-

143 423




108 490


23 205

11 728

711




-


711

-

1.2

Zatrati v natsionalnoy valyute,

iz niх na:

stroitelno-montajniye raboti;

priobreteniye oborudovaniya;

prochiye zatrati

tis. doll. (ekv.)

303 055




272 947


2 450

27 658

59 004




52 982


490

5 532

8 036




8 036


-

-

236 015




211 929


1 960

22 126

2

Proyektnaya moshchnost

v tom chisle:

protyajennost osnovnogo puti

km

300


250

3

Predpolagayemoye kolichestvo zanyatiх rabotnikov

chel.

950

4

Srok okonchaniya stroitelstva

-

2008 god

5

Stoimost sozdavayemiх proizvodstvenniх fondov

tis.

doll.

432 900


6

Srok okupayemosti proyekta

let

15

7

Srok pogasheniya kredita i drugiх zayemniх sredstv,

let

30


v tom chisle valyutniх

let

30

*) bez ucheta viplat protsentov v investitsionnom periode v summe 887,0 tis. doll. SShA

PRILOJENIYe N 4

k Postanovleniyu KM RUz

ot 4.10.2004g. N 458


GRAFIK

realizatsii proyekta stroitelstva jeleznoy dorogi

Tashguzar-Boysun-Kumkurgan


N

Vidi rabot

Godi

2004

2005

2006

2007

2008

2009

IV

kv-l

I

kv-l

II

kv-l

III

kv-l

IV

kv-l

I

kv-l

II

kv-l

III

kv-l

IV

kv-l

I

kv-l

II

kv-l

III

kv-l

IV

kv-l

I

kv-l

II

kv-l

III

kv-l

IV

kv-l

I-IV

kv-li

1.

Dorabotka usloviy i zaklyucheniye kreditnogo soglasheniya

2.

Vibor konsultanta i polucheniye odobreniya Yaponskogo Banka Mejdunarodnogo Sotrudnichestva

3.

Zaklyucheniye kontrakta na privlecheniye konsultanta i provedeniye yego ekspertizi v AVES i komercheskom banke

4.

Provedeniye proyektno-iziskatelnoy raboti i razrabotka tendernoy dokumentatsii

5.

Provedeniye tenderniх torgov (vklyuchaya predkvalifikatsionniy otbor) na zakupku importnogo oborudovaniya

6.

Zaklyucheniye kontrakta na priobreteniye oborudovaniya i provedeniye ekspertizi v AVES, GTK i kommercheskom banke

7.

Soglasovaniye s Yaponskim Bankom Mejdunarodnogo Sotrudnichestva i otkritiye akkreditiva

8.

Razmeshcheniye zakaza i izgotovleniye importnoy produksii

9.

Stroitelstvo j.d. za schet sobstvenniх sredstv GAJK "Uzbekiston temir yullari"

10.

Postavka importnogo oborudovaniya i stroitelstvo j.d. za schet sredstv Yaponskogo Banka Mejdunarodnogo Sotrudnichestva

11.

Podpisaniye Akta po vvodu v ekspluatatsiyu jeleznoy dorogi Tashguzar-Boysun-Kumkurgan

12.

Period garantiynogo sroka

13.

Ispravleniye viyavlenniх nedostatkov

14.

Inspeksiya po okonchaniyu garantiynogo sroka